4VAC25-130-817.84. Coal mine waste; impounding structures.
New and existing impounding structures constructed of coal mine waste or intended to impound coal mine waste shall meet the requirements of 4VAC25-130-817.81 and the additional requirements of this section.
(a) Coal mine waste shall not be used for construction of impounding structures unless it has been demonstrated to the division that the stability of such a structure conforms to the requirements of this Part and the use of coal mine waste will not have a detrimental effect on downstream water quality or the environment due to acid seepage through the impounding structure. The stability of the structure and the potential impact of acid mine seepage through the impounding structure shall be discussed in detail in the design plan submitted to the division in accordance with 4VAC25-130-784.16.
(b)(1) Each impounding structure constructed of coal mine waste or intended to impound coal mine waste shall be designed, constructed and maintained in accordance with 4VAC25-130-817.49(a) and (c). Such structures may not be retained permanently as part of the approved postmining land use.
(2) Each impounding structure constructed of coal mine waste or intended to impound coal mine waste that meets the criteria of 30 CFR 77.216(a) shall have sufficient spillway capacity to safely pass, adequate storage capacity to safely contain or a combination of storage capacity and spillway capacity to safely control, the probable maximum precipitation of a 6-hour precipitation event, or greater event as specified by the division.
(c) Spillways and outlet works shall be designed to provide adequate protection against erosion and corrosion. Inlets shall be protected against blockage.
(d) Drainage control. Runoff from areas above the disposal facility or runoff from the surface of the facility that may cause instability or erosion of the impounding structure shall be diverted into stabilized diversion channels designed to meet the requirements of 4VAC25-130-817.43 and designed to safely pass the runoff from a 100-year, 6-hour design precipitation event.
(e) Impounding structures constructed of or impounding coal mine waste shall be designed so that at least 90 percent of the water stored during the design precipitation event can be removed within a 10-day period.
(f) For an impounding structure constructed of or impounding coal mine waste, at least 90 percent of the water stored during the design precipitation event shall be removed within the 10-day period following the design precipitation event.
Statutory Authority
§§ 45.1-161.3 and 45.1-230 of the Code of Virginia.
Historical Notes
Derived from VR480-03-19 § 817.84, eff. December 15, 1981; amended, eff. June 28, 1982; October 28, 1982; December 14, 1982; October 11, 1983; December 27, 1983; May 8, 1984; June 22, 1984; August 2, 1984; October 16, 1985; January 7, 1987; July 22, 1987; November 25, 1987; October 12, 1988; December 26, 1990; July 1, 1991; July 17, 1991; November 20, 1991; July 7, 1992; May 5, 1993; October 19, 1994.