9VAC25-20-40. Applicability.

A. This chapter applies to:

1. All applicants for issuance of a new permit, permit authorization or certificate, or reissuance of an existing permit, permit authorization or certificate, except as specifically exempt under 9VAC25-20-50 A. The fee due shall be as specified under 9VAC25-20-110 or 9VAC25-20-130.

2. All permit, permit authorization or certificate holders who request that an existing permit, permit authorization or certificate be modified, except as specifically exempt under 9VAC25-20-50 A 3 or 9VAC25-20-50 A 6. The fee due shall be as specified under 9VAC25-20-120.

3. All land appliers land applying biosolids or industrial residuals on permitted sites in the Commonwealth of Virginia. The fee due shall be as specified under 9VAC25-20-146.

B. An applicant for a permit, permit authorization or certificate involving a permit that is to be revoked and reissued shall be considered an applicant for a new permit. The fee due shall be as specified under 9VAC25-20-110.

C. Permit maintenance fees apply to each Virginia Pollutant Discharge Elimination System (VPDES) permit holder and each Virginia Pollution Abatement (VPA) permit holder, except those specifically exempt under 9VAC25-20-50 B of this chapter. The fee due shall be as specified under 9VAC25-20-142.

D. Virginia Water Protection (VWP) Individual/Minimum Instream Flow permit fees apply to any permit for the construction of an intake on a stream or river, or to any permit for the construction of a new intake on an existing reservoir. The fee due shall be as specified under 9VAC25-20-110 or 9VAC25-20-120, as applicable.

E. VWP Individual/Reservoir permit fees apply to any permit for the construction of a new reservoir, or the expansion of an existing reservoir in which one of the purposes of the reservoir is for water supply. The fee due shall be as specified under 9VAC25-20-110 or 9VAC25-20-120, as applicable. VWP Individual/Reservoir permit fees do not apply to the construction of any impoundment, pond or lake in which water supply is not part of the project's purpose.

Statutory Authority

§§ 62.1-44.15:6, 62.1-44.16, and 62.1-44.19:3 of the Code of Virginia.

Historical Notes

Derived from VR680-01-01 § 1.4, eff. July 1, 1993; amended, Virginia Register Volume 20, Issue 23, eff. July 1, 2004; Volume 24, Issue 6, eff. January 1, 2008; Volume 31, Issue 24, eff. October 1, 2015; Volume 32, Issue 5, eff. January 1, 2016.

Website addresses provided in the Virginia Administrative Code to documents incorporated by reference are for the reader's convenience only, may not necessarily be active or current, and should not be relied upon. To ensure the information incorporated by reference is accurate, the reader is encouraged to use the source document described in the regulation.

As a service to the public, the Virginia Administrative Code is provided online by the Virginia General Assembly. We are unable to answer legal questions or respond to requests for legal advice, including application of law to specific fact. To understand and protect your legal rights, you should consult an attorney.