12VAC5-635-140. Installation inspection and correction.
A. Upon completion of the installation, alteration, or rehabilitation of a Tier 4 rainwater harvesting system ]:
1. The owner or agent shall submit to the local health department a statement signed by the installer certifying that the rainwater harvesting system was installed, altered, or rehabilitated in accordance with the construction permit and that the rainwater harvesting system complies with applicable state and local regulations, ordinances, and laws;
2. The designer shall thoroughly inspect the system installation to determine whether the installation was completed in accordance with the approved evaluation and design, including any revisions made pursuant to 12VAC5-635-130; and
3. The designer shall submit to the local health department a signed inspection report stating that the installation was completed in accordance with the approved evaluation and design revised only in accordance with the provisions of 12VAC5-635-130.
B. If the designer observes deficiencies during the inspection, the designer shall note the deficiencies in the inspection report and include a plan of correction that includes the specific corrective actions that will be taken to bring the rainwater harvesting system into compliance with this chapter, the date on which the corrective actions will be completed, and the date the designer will perform a follow-up inspection of the corrected rainwater harvesting system.
C. After the follow-up inspection, the designer shall submit a signed inspection report to the local health department affirming whether the corrective actions have been taken and whether the rainwater harvesting system is installed in compliance with the approved evaluation and design.
Statutory Authority
§§ 32.1-12 and 32.1-248.2 of the Code of Virginia.
Historical Notes
Derived from Virginia Register Volume 41, Issue 5, eff. November 20, 2024.