9VAC25-875-550. Erosion and sediment control plan requirements.
A. An erosion and sediment control plan shall be filed for a development and the buildings constructed within, regardless of the phasing of construction. The erosion and sediment control plan shall contain all major conservation decisions to ensure that the entire unit of land will be so treated to achieve the conservation objectives in 9VAC25-875-560. The erosion and sediment control plan may include:
1. Appropriate maps;
2. An appropriate soil and water plan inventory and management information with needed interpretations; and
3. A record of decisions contributing to conservation treatment.
B. The person responsible for carrying out the plan shall provide the name of an individual holding a certificate who will be in charge of and responsible for carrying out the land-disturbing activity to the VESCP or VESMP authority. However, the VESCP or VESMP authority may waive the Responsible Land Disturber Certificate requirement for an agreement in lieu of a plan in accordance with § 62.1-44.15:34 or 62.1-44.15:55 of the Code of Virginia.
C. If individual lots or sections in a residential development are being developed by different property owners, all land-disturbing activities related to the building construction shall be covered by an erosion and sediment control plan or an agreement in lieu of a plan signed by the property owner.
D. Land-disturbing activity of less than 10,000 square feet on individual lots in a residential development shall not be considered exempt from the provisions of the VESMA, ESCL, or this chapter if the total land-disturbing activity in the development is equal to or greater than 10,000 square feet.
Statutory Authority
§ 62.1-44.15:28 of the Code of Virginia.
Historical Notes
Derived from Virginia Register Volume 40, Issue 8, eff. July 1, 2024.