9VAC25-91-40. Compliance dates.

A. Every operator shall comply with this chapter on its effective date unless a later date is otherwise specified.

B. Operators of facilities existing on June 24, 1998, and exempted under § 62.1-44.34:17 D of the Code of Virginia (i.e., facilities not engaged in the resale of oil) having an aboveground storage capacity of 25,000 gallons or greater of oil must have complied with Part III (9VAC25-91-130 et seq., Pollution Prevention Requirements) of this chapter on or before October 22, 1998, unless otherwise specified in this chapter. If compliance with Part III of this chapter necessitates extensive upgrades to the existing facility design, these exempted operators shall have submitted a proposed extended compliance schedule and supporting explanation to the department no later than September 22, 1998, or such date approved by the department.

C. Operators of ASTs and facilities existing prior to June 24, 1998, and previously registered in accordance with the requirements of § 62.1-44.34:19.1 of the Code of Virginia shall not have to resubmit the registration form until five years from the date of the initial registration unless title to that AST or facility is transferred (i.e., change of ownership) or the AST is converted or brought back into use after permanent closure, whichever occurs first.

D. Operators of facilities subject to Part IV (9VAC25-91-170, Oil Discharge Contingency Plan (ODCP) Requirements) of this chapter that were brought into use on or after June 24, 1998, shall submit a complete application meeting all applicable requirements of this chapter no later than 90 days prior to commencement of operations.

1. The operator must receive approval of the ODCP by the department prior to commencement of facility operations.

2. The operators of facilities that have previously met the provisions of § 62.1-44.34:15 of the Code of Virginia for ODCP submittal shall not be required to resubmit the ODCP until 90 days prior to the date that plan's approval expires. Ninety days prior to the expiration of approval of the ODCP, the facility operator shall submit an updated plan or certification of renewal of an existing plan according to 9VAC25-91-170 F.

E. An operator having obtained approval of the ODCP shall operate, maintain, monitor, and keep records pertaining to 9VAC25-91-170 A 18 of Part IV (9VAC25-91-170, Oil Discharge Contingency Plan (ODCP) Requirements) of this chapter and under the provisions of Part III (9VAC25-91-130 et seq., Pollution Prevention Requirements) of this chapter.

Statutory Authority

§§ 62.1-44.15, 62.1-44.34:15, 62.1-44.34:15.1 and 62.1-44.34:19.1 of the Code of Virginia.

Historical Notes

Derived from Virginia Register Volume 14, Issue 18, eff. June 24, 1998; amended, Virginia Register Volume 31, Issue 26, eff. November 1, 2015; Volume 39, Issue 5, eff. November 23, 2022.

Website addresses provided in the Virginia Administrative Code to documents incorporated by reference are for the reader's convenience only, may not necessarily be active or current, and should not be relied upon. To ensure the information incorporated by reference is accurate, the reader is encouraged to use the source document described in the regulation.

As a service to the public, the Virginia Administrative Code is provided online by the Virginia General Assembly. We are unable to answer legal questions or respond to requests for legal advice, including application of law to specific fact. To understand and protect your legal rights, you should consult an attorney.