9VAC5-40-6510. Permits.
A permit may be required prior to beginning any of the activities specified below if the provisions of 9VAC5-50 (New and Modified Stationary Sources) and 9VAC5-80 (Permits for Stationary Sources) apply. Owners contemplating such action should review those provisions and contact the appropriate regional office for guidance on whether those provisions apply.
1. Construction of a facility.
2. Reconstruction (replacement of more than half) of a facility.
3. Modification (any physical change to equipment) of a facility.
4. Relocation of a facility.
5. Reactivation (re-startup) of a facility.
6. Operation of a facility.
Statutory Authority
§ 10.1-1308 of the Code of Virginia; federal Clean Air Act (§§ 110, 111, 123, 129, 171, 172, and 182); 40 CFR Parts 51 and 60.
Historical Notes
Derived from Virginia Register Volume 19, Issue 24, eff. September 10, 2003; amended, Virginia Register Volume 29, Issue 24, eff. August 28, 2013.