LIS

Administrative Code

Creating a Report: Check the sections you'd like to appear in the report, then use the "Create Report" button at the bottom of the page to generate your report. Once the report is generated you'll then have the option to download it as a pdf, print or email the report.

Virginia Administrative Code
Title 9. Environment
Agency 5. State Air Pollution Control Board
Chapter 80. Permits for Stationary Sources
11/5/2024

9VAC5-80-2230. Significant amendment procedures.

A. The criteria for use of significant amendment procedures are as follows:

1. Significant amendment procedures shall be used for requesting permit amendments that do not qualify as minor permit amendments under 9VAC5-80-2220 or as administrative amendments under 9VAC5-80-2210.

2. Significant amendment procedures shall be used for those permit amendments that meet any of the following criteria:

a. Involve significant changes to existing monitoring, reporting, or record keeping requirements that would make the permit requirements less stringent, such as a change to the method of monitoring to be used, a change to the method of demonstrating compliance or a relaxation of reporting or recordkeeping requirements.

b. Require or change a case-by-case determination of an emissions limitation or other requirement.

c. Seek to establish or change a permit term or condition (i) for which there is no corresponding underlying applicable regulatory requirement and (ii) that the source has assumed to avoid an applicable regulatory requirement to which the source would otherwise be subject. Such terms and conditions include, but are not limited to, an emissions cap assumed to avoid classification as a modification under the new source review program.

B. A request for a significant permit amendment shall include a description of the change, the emissions resulting from the change, and any new applicable regulatory requirements that will apply if the change occurs. The applicant may, at the applicant's discretion, include a suggested draft permit amendment.

C. The provisions of 9VAC5-80-2070 shall apply to requests made under this section.

D. The department will normally take final action on significant permit amendments within 180 days after receipt of a complete request. The department may extend this time period if additional information is needed.

E. The owner shall not make the change applied for in the significant amendment request until the amendment is approved by the department under subsection D of this section.

Statutory Authority

§ 10.1-1308 of the Code of Virginia.

Historical Notes

Derived from Virginia Register Volume 18, Issue 14, eff. May 1, 2002; amended, Virginia Register Volume 22, Issue 23, eff. September 1, 2006; Volume 25, Issue 6, eff. December 31, 2008; Volume 25, Issue 20, eff. July 23, 2009; Volume 39, Issue 5, eff. November 23, 2022.

Website addresses provided in the Virginia Administrative Code to documents incorporated by reference are for the reader's convenience only, may not necessarily be active or current, and should not be relied upon. To ensure the information incorporated by reference is accurate, the reader is encouraged to use the source document described in the regulation.

As a service to the public, the Virginia Administrative Code is provided online by the Virginia General Assembly. We are unable to answer legal questions or respond to requests for legal advice, including application of law to specific fact. To understand and protect your legal rights, you should consult an attorney.