LIS

Administrative Code

Creating a Report: Check the sections you'd like to appear in the report, then use the "Create Report" button at the bottom of the page to generate your report. Once the report is generated you'll then have the option to download it as a pdf, print or email the report.

Virginia Administrative Code
Title 9. Environment
Agency 5. State Air Pollution Control Board
Chapter 80. Permits for Stationary Sources
11/21/2024

9VAC5-80-470. Units with repowering extension plans.

A. No later than January 1, 2000, the designated representative of a unit governed by an approved repowering plan shall submit to the administrator and the department:

1. Satisfactory documentation of a preliminary design and engineering effort.

2. A binding letter agreement for the executed and binding contract (or for each in a series of executed and binding contracts) for the majority of the equipment to repower the unit using the technology conditionally approved by the administrator under 40 CFR 72.44(d)(3).

3. The letter agreement under subdivision 2 of this subsection shall be signed and dated by each party and specify:

a. The parties to the contract;

b. The date each party executed the contract;

c. The unit to which the contract applies;

d. A brief list identifying each provision of the contract;

e. Any dates to which the parties agree, including construction completion date;

f. The total dollar amount of the contract; and

g. A statement that a copy of the contract is on site at the source and will be submitted upon written request of the administrator or the department.

B. The designated representative of a unit governed by an approved repowering plan shall notify the administrator and the department in writing at least 60 days in advance of the date on which the existing unit is to be removed from operation so that the qualified repowering technology can be installed, or is to be replaced by another unit with the qualified repowering technology, in accordance with the plan.

C. Not later than 60 days after the units repowered under an approved repowering plan commences operation at full load, the designated representative of the unit shall submit a report to the administrator and the department comparing the actual hourly emissions and percent removal of each pollutant controlled at the unit to the actual hourly emissions and percent removal at the existing unit under the plan prior to repowering, determined in accordance with 40 CFR Part 75.

D. If at any time before the end of the repowering extension and before completion of construction and start-up testing, the owners and operators decide to terminate good faith efforts to design, construct, and test the qualified repowering technology on the unit to be repowered under an approved repowering plan, then the designated representative shall submit a notice to the administrator and the department by the earlier of the end of the repowering extension or a date within 30 days of such decision, stating the date on which the decision was made.

Statutory Authority

§ 10.1-1308 of the Code of Virginia.

Historical Notes

Derived from Virginia Register Volume 12, Issue 25, eff. October 15, 1996; amended, Virginia Register Volume 17, Issue 4, eff. January 1, 2001; Volume 39, Issue 5, eff. November 23, 2022.

Website addresses provided in the Virginia Administrative Code to documents incorporated by reference are for the reader's convenience only, may not necessarily be active or current, and should not be relied upon. To ensure the information incorporated by reference is accurate, the reader is encouraged to use the source document described in the regulation.

As a service to the public, the Virginia Administrative Code is provided online by the Virginia General Assembly. We are unable to answer legal questions or respond to requests for legal advice, including application of law to specific fact. To understand and protect your legal rights, you should consult an attorney.