20VAC5-314-90. Commissioning tests.
Commissioning tests of the IC's installed equipment shall be performed pursuant to applicable codes and standards, including IEEE 1547.1, Standard Conformance Test Procedures for Equipment Interconnecting Distributed Resources with Electric Power Systems, 2005. The utility shall be given at least five business days written notice, or notice as otherwise mutually agreed to in writing by the parties, of the tests to be performed, and the utility shall be allowed to witness the commissioning tests. The utility shall not be compensated by the IC for witnessing commissioning tests.
Statutory Authority
§§ 12.1-13 and 56-578 of the Code of Virginia.
Historical Notes
Derived from Virginia Register Volume 25, Issue 20, eff. May 21, 2009; amended, Virginia Register Volume 37, Issue 1, eff. October 15, 2020.