6VAC15-81-420. Bids.
A. Prior experience with jail construction is an element to be considered when selecting a contractor.
B. After bids for construction have been received and opened, and the owner has determined to proceed with the project, the owner or owner's agent shall submit a copy of the bid tabulation to the reviewing authority.
C. For projects utilizing nontraditional process, other than design-bid-build, the schedule of values shall be submitted within 45 days after award of the construction contract.
Statutory Authority
§§ 53.1-5, 53.1-80, and 53.1-82 of the Code of Virginia.
Historical Notes
Derived from Virginia Register Volume 34, Issue 12, eff. March 8, 2018.