9VAC25-740-30. Applicability and transition.
A. The requirements of this chapter shall apply to water reclamation systems, reclaimed water distribution systems, and water reuse unless specifically excluded under 9VAC25-740-50 A. The requirements shall apply to all new water reclamation systems, reclaimed water distribution systems and, as applicable, water reuses for which Virginia Pollution Abatement (VPA) or Virginia Pollutant Discharge Elimination System (VPDES) permit applications are received after October 1, 2008. The requirements may also be applied to all existing permitted facilities producing, distributing or using reclaimed water through a permit modification or reissuance procedure and shall be applied when such facilities are to be modified or expanded unless specifically excluded under 9VAC25-740-50 A. The owners of existing water reclamation systems, reclaimed water distribution systems and, as applicable, water reuses that do not have a VPA or VPDES permit shall submit a complete VPA or VPDES permit application or other necessary information as prescribed under 9VAC25-740-40 within 180 days of being requested by the department.
B. For the purposes of this chapter:
1. The incorporation of standards, monitoring requirements and special conditions for water reclamation and reuse into a VPA permit shall be considered a minor modification unless they alter other conditions of the permit specifically related to the pollutant management activity for which the permit was originally issued.
2. Standards, monitoring requirements and special conditions for water reclamation and reuse may be authorized for a VPDES permit through:
a. A modification of the permit where such standards, monitoring requirements, and special conditions would effectively alter other conditions of the permit specifically related to the effluent discharge for which the permit was originally issued, or where the diversion of source water from the VPDES permitted discharge to water reclamation and reuse has the potential to cause a significant adverse impact to other beneficial uses of the receiving state water, or both; or
b. An administrative authorization where such standards, monitoring requirements, and special conditions would not alter other conditions of the permit specifically related to the effluent discharge for which the permit was originally issued, and where the diversion of source water from the VPDES permitted discharge to water reclamation and reuse does not have the potential to cause a significant adverse impact to other beneficial uses of the receiving state water. The administrative authorization shall have the full effect of the VPDES permit until such time that it is incorporated into the VPDES permit through reissuance or modification.
3. Modification of a VPA or VPDES permit or the issuance of an administrative authorization associated with a VPDES permit described in subdivisions 1 and 2 of this subsection shall require an application in accordance with 9VAC25-740-100.
Statutory Authority
§ 62.1-44.15 of the Code of Virginia.
Historical Notes
Derived from Virginia Register Volume 24, Issue 26, eff. October 1, 2008; amended, Virginia Register Volume 30, Issue 9, eff. January 29, 2014; Volume 39, Issue 5, eff. November 23, 2022.