9VAC25-870-108. Stormwater management plan review.

A. A VSMP authority shall review and approve stormwater management plans.

B. A VSMP authority shall approve or disapprove a stormwater management plan according to the following:

1. The VSMP authority shall determine the completeness of a plan in accordance with 9VAC25-870-55, and shall notify the applicant of any determination, within 15 calendar days of receipt. Where available to the applicant, electronic communication may be considered communication in writing.

a. If within those 15 calendar days the plan is deemed to be incomplete, the applicant shall be notified in writing of the reasons the plan is deemed incomplete.

b. If a determination of completeness is made and communicated to the applicant within the 15 calendar days, an additional 60 calendar days from the date of the communication will be allowed for the review of the plan.

c. If a determination of completeness is not made and communicated to the applicant within the 15 calendar days, the plan shall be deemed complete as of the date of submission and a total of 60 calendar days from the date of submission will be allowed for the review of the plan.

d. The VSMP authority shall review, within 45 calendar days of the date of resubmission, any plan that has been previously disapproved.

2. During the review period, the plan shall be approved or disapproved and the decision communicated in writing to the person responsible for the land-disturbing activity or his designated agent. If the plan is not approved, the reasons for not approving the plan shall be provided in writing. Approval or denial shall be based on the plan's compliance with the requirements of this chapter and of the VSMP authority. Where available to the applicant, electronic communication may be considered communication in writing.

3. If a plan meeting all requirements of this chapter and of the VSMP authority is submitted and no action is taken within the time specified above, the plan shall be deemed approved.

C. Each approved plan may be modified in accordance with the following:

1. Modifications to an approved stormwater management plan shall be allowed only after review and written approval by the VSMP authority. The VSMP authority shall have 60 calendar days to respond in writing either approving or disapproving such requests.

2. Based on an inspection, the VSMP authority may require amendments to the approved stormwater management plan to address any deficiencies within a time frame set by the VSMP authority.

D. Upon the development of an online reporting system by the department, but no later than July 1, 2014, a VSMP authority shall then be required to obtain evidence of state permit coverage, where it is required, prior to providing approval to begin land disturbance.

E. The VSMP authority shall require the submission of a construction record drawing for permanent stormwater management facilities in accordance with 9VAC25-870-55. A VSMP authority may elect not to require construction record drawings for stormwater management facilities for which maintenance agreements are not required pursuant to 9VAC25-870-112.

Statutory Authority

§§  62.1-44.15:25 and 62.1-44.15:28 of the Code of Virginia.Historical Notes

Historical Notes

Former 4VAC50-60-108 derived from Virginia Register Volume 27, Issue 26, eff. September 13, 2011; amended, Virginia Register Volume 29, Issue 4, eff. November 21, 2012; amended and renumbered, Virginia Register Volume 30, Issue 2, eff. October 23, 2013.

Website addresses provided in the Virginia Administrative Code to documents incorporated by reference are for the reader's convenience only, may not necessarily be active or current, and should not be relied upon. To ensure the information incorporated by reference is accurate, the reader is encouraged to use the source document described in the regulation.

As a service to the public, the Virginia Administrative Code is provided online by the Virginia General Assembly. We are unable to answer legal questions or respond to requests for legal advice, including application of law to specific fact. To understand and protect your legal rights, you should consult an attorney.