9VAC25-875-330. Inspections.
A. The VESCP authority (i) shall provide for periodic inspections of the land-disturbing activity and require that an individual holding a certificate, as provided by § 62.1-44.15:52 of the Code of Virginia, will be in charge of and responsible for carrying out the land-disturbing activity and (ii) may require monitoring and reporting from the person responsible for carrying out the erosion and sediment control plan, to ensure compliance with the approved plan and to determine whether the measures required in the plan are effective in controlling erosion and sediment. However, any VESCP authority may waive the certificate requirement for an agreement in lieu of a plan.
B. Periodic inspections by the VESCP authority are required on all projects. The VESCP authority shall either:
1. Provide for an inspection during or immediately following initial installation of erosion and sediment controls, at least once in every two-week period, within 48 hours following any runoff producing storm event, and at the completion of the project prior to the release of any performance bonds; or
2. Establish an alternative inspection program that ensures compliance with the approved erosion and sediment control plan. Any alternative inspection program shall be:
a. Approved by the department prior to implementation;
b. Established in writing;
c. Based on a system of priorities that, at a minimum, address the amount of disturbed project area, site conditions, and stage of construction; and
d. Documented by inspection records.
Statutory Authority
§ 62.1-44.15:28 of the Code of Virginia.
Historical Notes
Derived from Virginia Register Volume 40, Issue 8, eff. July 1, 2024.