Part IX. Standards of Practice and Conduct for Asbestos Project Designers
18VAC15-20-457. Duties and functions.
The duties and functions of a project designer include, but are not limited to, preparing an asbestos abatement project design, specifications for asbestos abatement projects and addenda to abatement specifications.
Statutory Authority
§ 54.1-501 of the Code of Virginia.
Historical Notes
Derived from Virginia Register Volume 18, Issue 6, eff. January 2, 2002.
18VAC15-20-458. Responsibilities.
The project design shall include, but is not limited to:
1. Scope of work.
2. Order of work.
3. Work methods and practices to be used.
4. Number and type of final air samples to be taken.
Statutory Authority
§ 54.1-501 of the Code of Virginia.
Historical Notes
Derived from Virginia Register Volume 18, Issue 6, eff. January 2, 2002.