Part II. Administrative and Technical Criteria for Land-Disturbing Activities

9VAC25-870-40. Authority.

Pursuant to the Virginia Stormwater Management Act, the board is required to take actions ensuring the general health, safety, and welfare of the citizens of the Commonwealth as well as protecting the quality and quantity of state waters from the potential harm of unmanaged stormwater. In addition to other authority granted to the board under the Stormwater Management Act, the board is authorized pursuant to §§ 62.1-44.15:25 and 62.1-44.15:28 of the Code of Virginia to adopt regulations that specify standards and procedures for VSMPs, to establish statewide standards for stormwater management for land-disturbing activities, and to protect properties, the quality and quantity of state waters, the physical integrity of stream channels, and other natural resources.

Statutory Authority

§§  62.1-44.15:25 and 62.1-44.15:28 of the Code of Virginia.

Historical Notes

Former 4VAC50-60-40 derived from Virginia Register Volume 21, Issue 3, eff. January 29, 2005; amended, Virginia Register Volume 27, Issue 26, eff. September 13, 2011; Volume 29, Issue 4, eff. November 21, 2012; amended and renumbered, Virginia Register Volume 30, Issue 2, eff. October 23, 2013.

9VAC25-870-45. Implementation date.

The technical criteria in Part II A and Part II B shall be implemented by a VSMP authority when a General Permit for Discharges of Stormwater from Construction Activities has been issued that incorporates such criteria. Until that time, the required technical criteria shall be found in Part II C. VSMPs adopted in accordance with the Act and this chapter shall become effective July 1, 2014, unless otherwise specified by the department.

Statutory Authority

§§ 62.1-44.15:25 and 62.1-44.15:28 of the Code of Virginia.

Historical Notes

Former 4VAC50-60-45 derived from Virginia Register Volume 27, Issue 26, eff. September 13, 2011; amended, Virginia Register Volume 29, Issue 4, eff. November 21, 2012; renumbered, Virginia Register Volume 30, Issue 2, eff. October 23, 2013; Volume 38, Issue 25, eff. August 31, 2022.

9VAC25-870-46. General objectives.

The physical, chemical, biological, and hydrologic characteristics and the water quality and quantity of the receiving state waters shall be maintained, protected, or improved in accordance with the requirements of this part. Objectives include, but are not limited to, supporting state designated uses and water quality standards. All control measures used shall be employed in a manner that minimizes impacts on receiving state waters.

Statutory Authority

§§  62.1-44.15:25 and 62.1-44.15:28 of the Code of Virginia.

Historical Notes

Former 4VAC50-60-46 derived from Virginia Register Volume 27, Issue 26, eff. September 13, 2011; renumbered, Virginia Register Volume 30, Issue 2, eff. October 23, 2013.

9VAC25-870-47. Applicability of other laws and regulations; time limits on applicability of approved design criteria.

A. Nothing in this chapter shall be construed as limiting the applicability of other laws and regulations, including, but not limited to, the CWA, Virginia Stormwater Management Act, Virginia Erosion and Sediment Control Law, and the Chesapeake Bay Preservation Act, except as provided in § 62.1-44.15:27 K of the Code of Virginia, and all applicable regulations adopted in accordance with those laws, or the rights of other federal agencies, state agencies, or local governments to impose more stringent technical criteria or other requirements as allowed by law.

B. Land-disturbing activities that obtain an initial state permit or commence land disturbance prior to July 1, 2014, shall be conducted in accordance with the Part II C (9VAC25-870-93 et seq.) technical criteria of this chapter. Such projects shall remain subject to the Part II C technical criteria for two additional state permit cycles. After such time, portions of the project not under construction shall become subject to any new technical criteria adopted by the board.

C. Land-disturbing activities that obtain an initial state permit on or after July 1, 2014, shall be conducted in accordance with the Part II B (9VAC25-870-62 et seq.) technical criteria of this chapter, except as provided for in 9VAC25-870-48. Land-disturbing activities conducted in accordance with the Part II B technical criteria shall remain subject to the Part II B technical criteria for two additional state permit cycles. After such time, portions of the project not under construction shall become subject to any new technical criteria adopted by the board.

D. Nothing in this section shall preclude an operator from constructing to a more stringent standard at his discretion.

Statutory Authority

§§ 62.1-44.15:25 and 62.1-44.15:28 of the Code of Virginia.

Historical Notes

Former 4VAC50-60-47 and 4VAC50-60-47.1 derived from Virginia Register Volume 27, Issue 26, eff. September 13, 2011; amended, Virginia Register Volume 29, Issue 4, eff. November 21, 2012; amended and renumbered, Virginia Register Volume 30, Issue 2, eff. October 23, 2013; amended, Volume 30, Issue 11, eff. February 26, 2014.

9VAC25-870-48. Grandfathering.

A. Any land-disturbing activity shall be considered grandfathered by the VSMP authority and shall be subject to the Part II C (9VAC25-870-93 et seq.) technical criteria of this chapter provided:

1. A proffered or conditional zoning plan, zoning with a plan of development, preliminary or final subdivision plat, preliminary or final site plan, or any document determined by the locality to be equivalent thereto (i) was approved by the locality prior to July 1, 2012, (ii) provided a layout as defined in 9VAC25-870-10, (iii) will comply with the Part II C technical criteria of this chapter, and (iv) has not been subsequently modified or amended in a manner resulting in an increase in the amount of phosphorus leaving each point of discharge, and such that there is no increase in the volume or rate of runoff;

2. A state permit has not been issued prior to July 1, 2014; and

3. Land disturbance did not commence prior to July 1, 2014.

B. Locality, state, and federal projects shall be considered grandfathered by the VSMP authority and shall be subject to the Part II C technical criteria of this chapter provided:

1. There has been an obligation of locality, state, or federal funding, in whole or in part, prior to July 1, 2012, or the department has approved a stormwater management plan prior to July 1, 2012;

2. A state permit has not been issued prior to July 1, 2014; and

3. Land disturbance did not commence prior to July 1, 2014.

C. Land disturbing activities grandfathered under subsections A and B of this section shall remain subject to the Part II C technical criteria of this chapter for one additional state permit cycle. After such time, portions of the project not under construction shall become subject to any new technical criteria adopted by the board.

D. In cases where governmental bonding or public debt financing has been issued for a project prior to July 1, 2012, such project shall be subject to the technical criteria of Part II C.

E. Nothing in this section shall preclude an operator from constructing to a more stringent standard at his discretion.

Statutory Authority

§§ 62.1-44.15:25 and 62.1-44.15:28 of the Code of Virginia.

Historical Notes

Former 4VAC50-60-48 derived from Virginia Register Volume 27, Issue 26, eff. September 13, 2011; amended, Virginia Register Volume 29, Issue 4, eff. November 21, 2012; renumbered, Virginia Register Volume 30, Issue 2, eff. October 23, 2013; amended, Volume 30, Issue 11, eff. February 26, 2014.

9VAC25-870-51. Chesapeake Bay Preservation Act land-disturbing activity.

A. In order to protect the quality of state waters and to control the discharge of stormwater pollutants from land-disturbing activities, runoff associated with Chesapeake Bay Preservation Act land-disturbing activities shall be regulated by localities subject to the Chesapeake Bay Preservation Act or, in the case of state and federal agency projects, the department. In regulating such land-disturbing activities in accordance with subsection B of this section, localities shall have the same authority and responsibilities as set forth in these regulations for VSMP authorities.

B. After June 30, 2014, such land-disturbing activities shall not require completion of a registration statement or require coverage under the General Permit for Discharges of Stormwater from Construction Activities but shall be subject to the following technical criteria and program and administrative requirements:

1. An erosion and sediment control plan consistent with the requirements of the Virginia Erosion and Sediment Control Law and regulations must be designed and implemented during land disturbing activities. Prior to land disturbance, this plan must be approved by either the VESCP authority or the department in accordance with the Virginia Erosion and Sediment Control Law and attendant regulations.

2. A stormwater management plan consistent with the requirements of the Virginia Stormwater Management Act and regulations must be designed and implemented during the land-disturbing activity. The stormwater management plan shall be developed and submitted in accordance with 9VAC25-870-55. Prior to land disturbance, this plan must be approved by the VSMP authority.

3. Exceptions may be requested in accordance with 9VAC25-870-57.

4. Long-term maintenance of stormwater management facilities shall be provided for and conducted in accordance with 9VAC25-870-58.

5. Water quality design criteria in 9VAC25-870-63 shall be applied to the site.

6. Water quality compliance shall be achieved in accordance with 9VAC25-870-65.

7. Channel protection and flood protection shall be achieved in accordance with 9VAC25-870-66 or as permitted by subsection B of 9VAC25-870-52.

8. Offsite compliance options in accordance with 9VAC25-870-69 shall be available to Chesapeake Bay Preservation Act land-disturbing activities.

9. Such land-disturbing activities shall be subject to the design storm and hydrologic methods set out in 9VAC25-870-72, linear development controls in 9VAC25-870-76, and criteria associated with stormwater impoundment structures or facilities in 9VAC25-870-85.

Statutory Authority

§§ 62.1-44.15:25 and 62.1-44.15:28 of the Code of Virginia.

Historical Notes

Former 4VAC50-60-51 derived from Virginia Register Volume 27, Issue 26, eff. September 13, 2011; amended, Virginia Register Volume 29, Issue 4, eff. November 21, 2012; amended and renumbered, Virginia Register Volume 30, Issue 2, eff. October 23, 2013; amended, Virginia Register Volume 30, Issue 24, eff. July 1, 2014; Volume 35, Issue 4, eff. November 14, 2018.

9VAC25-870-52. Chesapeake Bay Preservation Act land-disturbing activities in rural Tidewater localities.

A. Acceptance of signed and sealed plans in lieu of local plan review. In lieu of a local plan review or retaining a local certified plan reviewer, a rural Tidewater locality may accept plans and supporting calculations for erosion and sediment control and stormwater management for any land-disturbing activity equal to or greater than 2,500 square feet but less than one acre if the following criteria are met:

1. The plans are prepared and submitted by a professional licensed to engage in practice in the Commonwealth under Chapter 4 (§ 54.1-400 et seq.) or 22 (§ 54.1-2200 et seq.) of Title 54.1 of the Code of Virginia and who shall hold a certificate of competence in the appropriate subject area, as provided in § 62.1-44.15:30 of the Code of Virginia; and

2. The plan and supporting calculations are appropriately signed and sealed by the professional with a certification that states: "This plan is designed in accordance with applicable state law and regulations."

B. Tiered approach to water quantity technical criteria compliance.

1. A rural Tidewater locality may adopt the following tiered approach to water quantity management based on the percent impervious cover of the watershed in accordance with this subsection for land-disturbing activities that disturb an area of 2,500 square feet or more but less than one acre:

a. For less than 5.0% impervious cover, apply the Virginia Erosion and Sediment Control Regulation Minimum Standard 19 in effect prior to July 1, 2014, adopted by the board pursuant to Article 2.4 (§ 62.1-44.15:51 et seq.) of Chapter 3.1 of Title 62.1 of the Code of Virginia, for the protection of downstream properties and waterways from sediment deposition, erosion, and damage due to increases in volume, velocity, and peak flow rate of stormwater runoff for the stated frequency storm of 24-hour duration.

b. For 5.0% or more impervious cover but less than 7.5%, detain and release over a 24-hour period the expected rainfall resulting from the one year, 24-hour storm, which practices shall be exempt from any flow rate capacity and velocity requirements for natural or man-made channels.

c. For 7.5% impervious cover or more, apply the water quantity technical criteria in accordance with 9VAC25-870-66.

2. The establishment and conduct of the tiered approach by the locality pursuant to this section shall be subject to review by the department.

3. Prior to the adoption and implementation of the tiered approach to water quantity management, the local governing body shall:

a. Develop a watershed map that includes the following:

(1) The boundaries of the locality and each watershed located partially or wholly within the locality based on the most recent version of Virginia's 6th order National Watershed Boundary Dataset;

(2) The percentage of impervious cover within each watershed. Data provided by the Virginia Geographic Information Network (VGIN) shall be sufficient for the initial determination of impervious cover percentage at the time of the initial adoption of the map; and

(3) The locations at which the governing body expects or proposes that development should occur and may indicate the projected future percentage of impervious cover based on proposed development. The governing body may designate certain areas within a watershed in which it proposes that denser-than-average development shall occur and may designate environmentally sensitive areas in which the water quantity technical criteria in 9VAC25-870-66 shall apply.

b. After the watershed map has been developed, the governing body may then approve and adopt the map by a majority vote of its membership and publish it as the official watershed map of the locality. No official watershed map shall be adopted by the governing body or have any effect until it is approved by an ordinance duly passed by the governing body of the locality after a public hearing, preceded by public notice as required by § 15.2-2204 of the Code of Virginia. Within 30 days after adoption of the official watershed map, the governing body shall file the watershed map in the office of the clerk of the circuit court.

4. At least once per year, the governing body shall by majority vote make additions to or modifications of the official watershed map to reflect actual development projects. The governing body shall change the indication on the map of the impervious cover percentage within a watershed where the percentage has changed and shall update the map and supporting datasets with actual development project information, including single-family housing projects and any projects covered by the General VPDES Permit for Discharges of Stormwater from Construction Activities and administered by the department for opt-out localities pursuant to § 62.1-44.15:27 of the Code of Virginia. The governing body may incorporate into the official watershed map the most recent VGIN data, including data on state and federal projects that are not reviewed or approved by the locality. The governing body shall keep current its impervious cover percentage for each watershed located within the locality, as reflected in the official watershed map, and shall make the map and such percentages available to the public.

5. The locality shall notify the department and update the official watershed map within 12 months of the approval of the development plan for any project that exceeds the percent impervious cover percentage of the watershed in which it is located and causes the impervious cover percentage for the watershed to increase such that the watershed percent impervious cover is categorized by the next higher tier pursuant to subdivision B 1 of this section.

6. No official watershed map or its adopting or amending ordinance shall take precedence over any duly adopted zoning ordinance, comprehensive plan, or other local land-use ordinance, and in the case of a conflict, the official watershed map or ordinance shall yield to such land-use ordinance.

Statutory Authority

§ 62.1-44.15:25 and 62.1-44.15:28 of the Code of Virginia.

Historical Notes

Derived from Virginia Register Volume 35, Issue 4, eff. November 14, 2018.

Website addresses provided in the Virginia Administrative Code to documents incorporated by reference are for the reader's convenience only, may not necessarily be active or current, and should not be relied upon. To ensure the information incorporated by reference is accurate, the reader is encouraged to use the source document described in the regulation.

As a service to the public, the Virginia Administrative Code is provided online by the Virginia General Assembly. We are unable to answer legal questions or respond to requests for legal advice, including application of law to specific fact. To understand and protect your legal rights, you should consult an attorney.