LIS

Code of Virginia

Creating a Report: Check the sections you'd like to appear in the report, then use the "Create Report" button at the bottom of the page to generate your report. Once the report is generated you'll then have the option to download it as a pdf, print or email the report.

Code of Virginia
Title 43. Mechanics' and Certain Other Liens
Chapter 1. Mechanics' and Materialmen's Liens
12/21/2024

§ 43-23. Priority among liens perfected under this chapter.

There shall be no priority among the liens created and perfected under this chapter, except that the lien of a subcontractor shall be preferred to that of his general contractor; the lien of persons performing labor or furnishing materials for a subcontractor, shall be preferred to that of such subcontractor; and liens filed by persons performing manual labor shall have priority over materialmen to the extent of the labor performed during the thirty days immediately preceding the date of the performance of the last labor.

Code 1919, § 6437; 1920, p. 485.

The chapters of the acts of assembly referenced in the historical citation at the end of this section may not constitute a comprehensive list of such chapters and may exclude chapters whose provisions have expired.