20VAC5-314-38. Queue number and interdependent projects.
A. Queue number and queue position. The utility shall assign a queue number to an interconnection request based upon the date-stamp and time-stamp of receipt of a completed Interconnection Request Form by the utility. A later received Interconnection Request Form shall be assigned a higher numerical queue number than an earlier received Interconnection Request Form. The queue number and relative position of each interconnection request will be used to determine the cost responsibility for the upgrades necessary to accommodate the interconnection.
B. Interdependent projects.
1. Upon an IC's submission of an interconnection request for the 20VAC5-314-40 Level 1 interconnection process, 20VAC5-314-60 Level 2 interconnection process, or 20VAC5-314-70 Level 3 interconnection process, the utility shall review the interconnection request and make a preliminary determination of whether any interdependencies exist between the IC's proposed SGF and any other IC with a lower queue number. If the interconnection request is for a standby SGF with zero export, then the proposed SGF shall be studied as a Project A. For all other interconnections, any preliminary determination by the utility that the SGF does not create an interdependency will result in the interconnection request being preliminarily designated as a Project A, and the utility shall proceed immediately to either the 20VAC5-314-40, 20VAC5-314-60, or 20VAC5-314-70 Level 1, 2, or 3 study process, as applicable. At the 20VAC5-314-70 B scoping meeting, the utility shall advise the IC regarding its preliminary determination of whether interdependency would be created by the SGF. If no 20VAC5-314-70 B scoping meeting is scheduled, then the utility shall notify the IC in writing within five business days after making its preliminary determination of whether interdependency would be created by the SGF. If applicable, the Project A IC will pay the interconnection request study deposit required for the 20VAC5-314-70 Level 3 study process as identified in Schedule 6 of 20VAC5-314-170 in conjunction with the execution of the initial study agreement delivered by the utility pursuant to 20VAC5-314-70. An SGF preliminarily reviewed for system impacts and designated as a Project A may still be determined later to create an interdependency and may then be redesignated by the utility as an interdependent project during the 20VAC314-70 D system impact study process, thereby losing its Project A designation. Once the system impact study report is issued by the utility and the report designates an SGF as a Project A for purposes of the 20VAC314-70 E facilities study, the interconnection request shall retain this Project A designation during the facilities study, without change.
2. If the utility determines that the IC's proposed SGF is interdependent with one other interconnection request with a lower queue number (i.e., an earlier submitted interconnection request), the utility shall notify the IC in writing or at the 20VAC5-314-70 B scoping meeting that the interconnection request is designated as a Project B.
a. Following the 20VAC5-314-70 B scoping meeting, the Project B IC shall then have the option to either:
(1) Wait without further advancement of the interconnection request until Project A has executed a final interconnection agreement and begun making payments for any required upgrades, customer interconnection facilities, and other charges under 20VAC314-50 F. Under this option, Project B is not required to adhere to the timeline in 20VAC5-314-70 C until Project A has signed an SGIA and begun making payments or withdrawn its interconnection request; or
(2) Proceed to the 20VAC314-70 D system impact study process. If the Project B IC chooses this option, the utility shall provide the Project B IC a Feasibility Study Agreement pursuant to 20VAC5-314-70 C or a System Impact Study Agreement pursuant to 20VAC5-314-70 D within 10 business days. If the Project B IC signs a System Impact Study Agreement and pays the interconnection request study deposit pursuant to Schedule 6 of 20VAC5-314-170, the Project B shall receive a system impact study report that assumes the Project A interconnection request with the lower queue number completes construction and interconnection, and another system impact study report that assumes the Project A interconnect request with the lower queue number is not constructed and is withdrawn. The Project B IC is responsible for all costs for studying with and without Project A.
b. The utility shall not proceed to a Project B facilities study until after the Project B IC returns a signed Facilities Study Agreement to the utility and the utility has issued the 20VAC314-70 E facilities study report for Project A. Once the Project A facilities study report has been issued, the Project B IC shall then have the option to either:
(1) Wait without further advancement of the interconnection request until Project A has executed a final interconnection agreement and begun making payments for any required upgrades, customer interconnection facilities, and other charges under 20VAC314-50 F. Under this option, Project B is not required to adhere to the timeline in 20VAC5-314-70 E until Project A has signed an SGIA and begun making payments or withdrawn its interconnection request; or
(2) Proceed with a 20VAC314-70 E facilities study process. If the Project B IC chooses this option, the utility shall provide the Project B IC a Facilities Study Agreement pursuant to 20VAC5-314-70 E within 10 business days. If the Project B IC signs a Facilities Study Agreement prior to Project A committing to construction by signing the final interconnection agreement and beginning to make payments, then Project B's facilities study shall assume that the Project A interconnection request with the lower queue number will complete construction and interconnection. If Project A is later canceled prior to the Project A IC making payment for the required upgrades, the utility shall revise the Project B facilities study at the Project B IC's expense.
3. If the utility determines that the IC's proposed SGF is interdependent with more than one other interconnection request with a lower queue number (i.e., an earlier submitted interconnection request), the utility shall notify the IC at the 20VAC5-314-70 B scoping meeting and describe generally the number and type of interdependencies of interconnection requests with lower queue numbers.
a. The utility shall not study a project if it is interdependent with more than one earlier queued project. The utility will study a project when interdependency with only one earlier queued project exists. The removal of interdependency with multiple projects may be the result of (i) upgrades to the utility system that eliminate the cause of the interdependency, (ii) withdrawal of interdependent projects with lower queue numbers, or (iii) a lower queue number project signing an interconnection agreement and making payments identified in their SGIA.
b. Within five business days of an interconnection request becoming a Project B interconnection request that is interdependent with only one other interconnection request with a lower queue number, the utility shall schedule the 20VAC5-314-70 B scoping meeting and provide the new Project B IC the options specified in subdivision 2 a of this subsection. Upon being designated by the utility as a Project B, the IC's queue number shall be used to determine the order in which the interconnection request is studied under 20VAC314-70 D relative to all other interconnection requests.
C. Interconnection requests submitted prior to October 15, 2020. Other than as set forth in 20VAC5-314-10 C, nothing in this chapter affects an IC's queue number assigned before October 15, 2020. Interconnection requests that have received a system impact study report as of October 15, 2020, that did not identify any interdependency with another project shall be deemed a Project A. Any interconnection requests for which the utility has not completed the system impact study and issued a system impact study report (or combined study report, as applicable) to the IC as of October 15, 2020, shall be reviewed for interdependency pursuant to this section.
Should an IC fail to comply with 20VAC5-314-10 C following receipt of written notice specifying how the IC failed to comply and the expiration of an opportunity to cure by the close of business on the 10th business day following the posted date of such notice to cure, the IC shall lose its queue number and the interconnection request shall be deemed withdrawn.
Statutory Authority
§§ 12.1-13 and 56-578 of the Code of Virginia.
Historical Notes
Derived from Virginia Register Volume 37, Issue 1, eff. October 15, 2020.