Title 56. Public Service Companies
Chapter 10.3. Underground Utility Damage Prevention Act
§ 56-265.22:1. Meetings between excavators and operators.
A. Any person planning excavation or demolition in such proximity to the underground utility lines that the utility lines may be destroyed, damaged, dislocated, or disturbed may request a meeting with the operator whose underground utility lines are located in the area of the proposed excavation or demolition to discuss the marking of such lines. The project requiring excavation shall be of sufficient complexity to require a pre-marking meeting. The meeting notice shall include all information required by § 56-265.18 and a specific time and location for the meeting.
B. The notification center shall, upon receiving a meeting notice, notify all member operators whose underground utility lines are located in the area of the proposed excavation or demolition. The notification center shall provide to the excavator the names of those operators being notified of the meeting.
C. The operators notified by the notification center shall meet with the excavator by 7:00 a.m. on the third working day following the excavator's meeting notice. If an operator does not agree to the excavator's suggested time and location, the operator shall set up a mutually agreeable time and location to meet no later than 7:00 a.m. on the third working day following the meeting notice.
D. The excavator's meeting notice shall not be the notice to excavate required under § 56-265.17. The notice to excavate required under § 56-265.17 for the project shall not be submitted to the notification center until after the meeting referenced in subsection A of this section has occurred, or after 7:00 a.m. on the third working day following the meeting notice.
2002, c. 841.