LIS

Code of Virginia

Creating a Report: Check the sections you'd like to appear in the report, then use the "Create Report" button at the bottom of the page to generate your report. Once the report is generated you'll then have the option to download it as a pdf, print or email the report.

Code of Virginia
Title 56. Public Service Companies
Chapter 23. Virginia Electric Utility Regulation Act
12/3/2024

§ 56-585.1:4. Development of solar and wind generation and energy storage capacity in the Commonwealth.

A. Prior to January 1, 2024, (i) the construction or purchase by a public utility of one or more solar or wind generation facilities located in the Commonwealth or off the Commonwealth's Atlantic shoreline, each having a rated capacity of at least one megawatt and having in the aggregate a rated capacity that does not exceed 5,000 megawatts, or (ii) the purchase by a public utility of energy, capacity, and environmental attributes from solar facilities described in clause (i) owned by persons other than a public utility is in the public interest, and the Commission shall so find if required to make a finding regarding whether such construction or purchase is in the public interest.

B. Prior to January 1, 2024, (i) the construction or purchase by a public utility of one or more solar or wind generation facilities located in the Commonwealth or off the Commonwealth's Atlantic shoreline, each having a rated capacity of less than one megawatt, including rooftop solar installations with a capacity of not less than 50 kilowatts, and having in the aggregate a rated capacity that does not exceed 500 megawatts, or (ii) the purchase by a public utility of energy, capacity, and environmental attributes from solar facilities described in clause (i) owned by persons other than a public utility is in the public interest, and the Commission shall so find if required to make a finding regarding whether such construction or purchase is in the public interest.

C. The aggregate cap of 5,000 megawatts of rated capacity described in clause (i) of subsection A, the aggregate cap of 500 megawatts of rated capacity described in clause (i) of subsection B, and the aggregate cap of 200 megawatts of rated capacity described in subsection I are separate and independent from each other. The capacity of facilities in subsection B shall not be counted in determining the capacity of facilities in subsection A or I; the capacity of facilities in subsection A shall not be counted in determining the capacity of facilities in subsection B or I; and the capacity of facilities in subsection I shall not be counted in determining the capacity of facilities in subsection A or B.

D. Twenty-five percent of the solar generation capacity placed in service on or after July 1, 2018, located in the Commonwealth, and found to be in the public interest pursuant to subsection A or B shall be from the purchase by a public utility of energy, capacity, and environmental attributes from solar facilities owned by persons other than a public utility. The remainder shall be construction or purchase by a public utility of one or more solar generation facilities located in the Commonwealth. All of the solar generation capacity located in the Commonwealth and found to be in the public interest pursuant to subsection A or B shall be subject to competitive procurement, provided that a public utility may select solar generation capacity without regard to whether such selection satisfies price criteria if the selection of the solar generating capacity materially advances non-price criteria, including favoring geographic distribution of generating capacity, areas of higher employment, or regional economic development, if such non-price solar generating capacity selected does not exceed 25 percent of the utility's solar generating capacity.

E. Construction, purchasing, or leasing activities for a test or demonstration project for a new utility-owned and utility-operated generating facility or facilities utilizing energy derived from offshore wind with an aggregate capacity of not more than 16 megawatts are in the public interest.

F. Prior to January 1, 2035, (i) the construction by a public utility of one or more energy storage facilities located in the Commonwealth, having in the aggregate a rated capacity that does not exceed 2,700 megawatts, or (ii) the purchase by a public utility of energy storage facilities described in clause (i) owned by persons other than a public utility or the capacity from such facilities is in the public interest, and the Commission shall so find if required to make a finding regarding whether such construction or purchase is in the public interest.

G. At least 35 percent of the energy storage capacity placed in service on or after July 1, 2020, located in the Commonwealth and found to be in the public interest pursuant to subsection F shall be from the purchase by a public utility of energy storage facilities owned by persons other than a public utility or the capacity from such facilities. All of the energy storage facilities located in the Commonwealth and found to be in the public interest pursuant to subsection F shall be subject to competitive procurement, provided that a public utility may select energy storage facilities without regard to whether such selection satisfies price criteria if the selection of the energy storage facilities materially advances non-price criteria, including favoring geographic distribution of generating facilities, areas of higher employment, or regional economic development, if such energy storage facilities selected for the advancement of non-price criteria do not exceed 25 percent of the utility's energy storage capacity.

H. A utility may elect to petition the Commission, outside of a triennial or biennial review proceeding conducted pursuant to § 56-585.1, at any time for a prudency determination with respect to the construction or purchase by the utility of one or more solar or wind generation facilities located in the Commonwealth or off the Commonwealth's Atlantic Shoreline or the purchase by the utility of energy, capacity, and environmental attributes from solar or wind facilities owned by persons other than the utility. The Commission's final order regarding any such petition shall be entered by the Commission not more than three months after the date of the filing of such petition.

I. Prior to January 1, 2024, (i) the construction or purchase by a public utility of one or more solar or wind generation facilities located on a previously developed project site in the Commonwealth having in the aggregate a rated capacity that does not exceed 200 megawatts or (ii) the purchase by a public utility of energy, capacity, and environmental attributes from solar facilities described in clause (i) owned by persons other than a public utility, is in the public interest.

2018, c. 296; 2020, cc. 1190, 1193, 1194, 1225; 2023, cc. 757, 775.

The chapters of the acts of assembly referenced in the historical citation at the end of this section may not constitute a comprehensive list of such chapters and may exclude chapters whose provisions have expired.