LIS

Code of Virginia

Creating a Report: Check the sections you'd like to appear in the report, then use the "Create Report" button at the bottom of the page to generate your report. Once the report is generated you'll then have the option to download it as a pdf, print or email the report.

Code of Virginia
Title 56. Public Service Companies
Chapter 23. Virginia Electric Utility Regulation Act
11/21/2024

§ 56-581. Regulation of rates subject to Commission's jurisdiction.

A. The Commission shall regulate the rates of investor-owned incumbent electric utilities for the transmission of electric energy, to the extent not prohibited by federal law, and for the generation of electric energy and the distribution of electric energy to retail customers pursuant to this section and § 56-585.1.

B. In any proceeding to review base rates for a Phase I Utility that commences after July 1, 2023, if the Commission determines in its sole discretion that the utility's existing base rates will, on a going-forward basis, either produce (i) revenues in excess of the utility's authorized rate of return or (ii) revenues below the utility's authorized rate of return, then, notwithstanding any provision of law governing rate proceedings, the Commission shall order any reductions or increases, as applicable and necessary, to such base rates that it deems appropriate to ensure the resulting base rates (a) are just and reasonable and (b) provide the utility an opportunity to recover its costs of providing services over the rate period ending on December 31 of the year of the utility's succeeding review and earn a fair rate of return authorized pursuant to the provisions governing such review proceeding. Such determination shall be limited to the Phase I Utility's base rates and shall not consider the costs or revenues recovered in any rate adjustment clause authorized pursuant to this chapter.

C. In any proceeding to review base rates for a Phase II Utility that commences after July 1, 2023, if the Commission determines in its sole discretion that the utility's existing base rates will, on a going-forward basis, either produce (i) revenues in excess of the utility's authorized rate of return or (ii) revenues below the utility's authorized rate of return, then, notwithstanding any provision of subdivision A 8 of § 56-585.1, the Commission shall order any reductions or increases, as applicable and necessary, to such base rates that it deems appropriate to ensure the resulting base rates (a) are just and reasonable and (b) provide the utility an opportunity to recover its costs of providing services over the rate period ending on December 31 of the year of the utility's succeeding review and earn a fair rate of return on its base rates as determined in subdivision A 2 of § 56-585.1. Such determination shall be limited to the Phase II Utility's base rates and shall not consider the costs or revenues recovered in any rate adjustment clause authorized pursuant to subdivision A 6 of § 56-585.1 that has not been combined with the utility's base rates. The Commission shall use the most recently ended 12-month test period, along with normalization of nonrecurring test period costs and annualized adjustments for future costs, as the basis for determining the appropriateness of any rate adjustment. In any such filing to review base rates, a Phase II Utility shall separately project future costs over each 12-month period ending on December 31 of the year of the utility's succeeding rate periods. The Commission may, to the extent it finds such action aligns with the utility's projected cost of service, direct that any reduction or increase to the utility's rates for generation and distribution services be implemented on a staggered basis at the commencement and midpoint of the succeeding rate period.

D. Beginning July 1, 1999, and thereafter, no cooperative that was a member of a power supply cooperative on January 1, 1999, shall be obligated to file any rate rider as a consequence of an increase or decrease in the rates, other than fuel costs, of its wholesale supplier, nor must any adjustment be made to such cooperative's rates as a consequence thereof.

E. Except for the provision of default services under § 56-585 or emergency services in § 56-586, nothing in this chapter shall authorize the Commission to regulate the rates or charges for electric service to the Commonwealth and its municipalities.

F. As used in this section:

"Base rates" means rates for generation and distribution services.

"Phase I Utility" has the same meaning as provided in subdivision A 1 of § 56-585.1.

"Phase II Utility" has the same meaning as provided in subdivision A 1 of § 56-585.1.

1999, c. 411; 2000, c. 991; 2007, cc. 888, 933; 2023, cc. 497, 498, 757, 775.

The chapters of the acts of assembly referenced in the historical citation at the end of this section may not constitute a comprehensive list of such chapters and may exclude chapters whose provisions have expired.