Title 2.2. Administration of Government
Chapter 43. Virginia Public Procurement Act
Article 4. Prompt Payment.
§ 2.2-4347. Definitions.As used in this article, unless the context requires a different meaning:
"Construction contract" means a contract relating to the construction, alteration, repair, or maintenance of a building, structure, or appurtenance to such building or structure, including moving, demolition, and excavation connected with such building or structure, or any provision contained in any contract relating to the construction of projects other than buildings.
"Contractor" or "general contractor" means the entity that has a direct contract with any "state agency" as defined herein or any agency of local government as discussed in § 2.2-4352.
"Debtor" means any individual, business, or group having a delinquent debt or account with any state agency that obligation has not been satisfied or set aside by court order or discharged in bankruptcy.
"Payment date" means either (i) the date on which payment is due under the terms of a contract for provision of goods or services or (ii) if such date has not been established by contract, (a) 30 days after receipt of a proper invoice by the state agency or its agent or 45 days after receipt by the local government or its agent responsible under the contract for approval of such invoices for the amount of payment due or (b) 30 days after receipt of the goods or services by the state agency or 45 days after receipt by the local government, whichever is later.
"State agency" means any authority, board, department, instrumentality, institution, agency, or other unit of state government. "State agency" does not include any county, city, or town or any local or regional governmental authority.
"Subcontractor" means any entity that has a contract to supply labor or materials to the contractor to whom the contract was awarded or to any subcontractor in the performance of the work provided for in such contract.
1984, c. 736, § 11-62.1; 1990, c. 824; 1992, c. 75; 2001, c. 844; 2023, cc. 675, 676.
§ 2.2-4348. Exemptions.The provisions of this article shall not apply to (i) the late payment provisions contained in any public utility tariffs prescribed by the State Corporation Commission or (ii) payments for services provided under the state plan for medical assistance identified as potentially fraudulent, abusive, or erroneous in accordance with the program established pursuant to § 32.1-319.1 and delayed until such time as the claim can be validated.
1984, c. 736, § 11-62.9; 2001, c. 844; 2017, c. 750.
§ 2.2-4349. Retainage to remain valid.Notwithstanding the provisions of this article, the provisions of § 2.2-4333 relating to retainage shall remain valid.
1984, c. 736, § 11-62.8; 2001, c. 844.
§ 2.2-4350. Prompt payment of bills by state agencies.A. Every state agency that acquires goods or services, or conducts any other type of contractual business with nongovernmental, privately owned enterprises shall promptly pay for the completely delivered goods or services by the required payment date.
Payment shall be deemed to have been made when offset proceedings have been instituted, as authorized under the Virginia Debt Collection Act (§ 2.2-4800 et seq.).
B. Separate payment dates may be specified for contracts under which goods or services are provided in a series of partial deliveries or executions to the extent that such contract provides for separate payment for such partial delivery or execution.
1984, c. 736, §§ 11-62.2, 11-62.3; 1992, c. 75; 2001, c. 844.
§ 2.2-4350.1. Prohibition on payment without an appropriation; prohibition on IOUs.A. As used in this section, "IOU" means a document issued by a governmental entity or representative (i) that acknowledges a debt but that does not specify all repayment terms, such as the repayment date, and (ii) when moneys are not available to pay a current debt.
B. 1. Notwithstanding any other provision of law, unless the General Assembly has appropriated funds to pay for a good or service or to make payment on a debt, no state department, agency, or other state entity nor any state official, officer, employee, or agent shall (i) attempt to pay for the good or service or attempt to make payment on the debt; (ii) issue any document or paper that guarantees payment, or purports to pay, for the good or service or guarantees payment, or purports to make payment, on the debt; or (iii) in any other way attempt to pay, guarantee payment, or purport to pay for the same.
2. The prohibition on payment under subdivision 1 shall not apply (i) to payments required by federal law or (ii) if funds are lawfully available.
C. In addition, in no case shall any (i) state department, agency, or other state entity or (ii) state official, officer, or employee in performing the duties of his position furnish an IOU in exchange for any good or service, as a means to pay for any good or service, or in lieu of a payment on a debt.
2015, c. 673.
§ 2.2-4351. Defect or impropriety in the invoice or goods and/or services received.In instances where there is a defect or impropriety in an invoice or in the goods or services received, the state agency shall notify the supplier of the defect or impropriety, if the defect or impropriety would prevent payment by the payment date. The notice shall be sent within fifteen days after receipt of the invoice or the goods or services.
1984, c. 736, § 11-62.4; 2001, c. 844.
§ 2.2-4352. Prompt payment of bills by localities.Every agency of local government that acquires goods or services, or conducts any other type of contractual business with a nongovernmental, privately owned enterprise, shall promptly pay for the completed delivered goods or services by the required payment date. The required payment date shall be either: (i) the date on which payment is due under the terms of the contract for the provision of the goods or services; or (ii) if a date is not established by contract, not more than forty-five days after goods or services are received or not more than forty-five days after the invoice is rendered, whichever is later.
Separate payment dates may be specified for contracts under which goods or services are provided in a series of partial executions or deliveries to the extent that the contract provides for separate payment for partial execution or delivery.
Within twenty days after the receipt of the invoice or goods or services, the agency shall notify the supplier of any defect or impropriety that would prevent payment by the payment date.
Unless otherwise provided under the terms of the contract for the provision of goods or services, every agency that fails to pay by the payment date shall pay any finance charges assessed by the supplier that shall not exceed one percent per month.
The provisions of this section shall not apply to the late payment provisions in any public utility tariffs or public utility negotiated contracts.
1985, c. 454, § 11-62.10; 2001, c. 844.
§ 2.2-4353. Date of postmark deemed to be date payment is made.In those cases where payment is made by mail, the date of postmark shall be deemed to be the date payment is made for purposes of this chapter.
1984, c. 736, § 11-62.6; 2001, c. 844.
§ 2.2-4354. Payment clauses to be included in contracts.Any contract awarded by any state agency, or any contract awarded by any agency of local government in accordance with § 2.2-4352, shall include:
1. A payment clause that obligates the contractor on a construction contract, in the event that the contractor has not received payment from the state agency or local government for work performed by a subcontractor under such contract, to be liable for the entire amount owed to such subcontractor and to pay such subcontractor within 60 days of the receipt of an invoice following satisfactory completion of the work for which the subcontractor has invoiced. Such contractor shall not be liable for amounts otherwise reducible due to the subcontractor's noncompliance with the terms of the contract. However, in the event that the contractor withholds all or a part of the amount invoiced by the subcontractor under the terms of the contract, the contractor shall notify the subcontractor within 50 days of the receipt of such invoice, in writing, of his intention to withhold all or a part of the subcontractor's payment with the reason for nonpayment, specifically identifying the contractual noncompliance, the dollar amount being withheld, and the lower-tier subcontractor responsible for the contractual noncompliance. Payment by the party contracting with the contractor shall not be a condition precedent to payment to any lower-tier subcontractor, regardless of that contractor's receiving payment for amounts owed to that contractor. Any provision in a construction contract contrary to this section shall be unenforceable. Nothing in this subdivision shall be construed to (i) apply to or prohibit the inclusion of any retainage provisions in a construction contract or (ii) apply to contracts awarded solely for professional services as that term is defined in § 2.2-4301 where the public body is contracting directly with an architectural and engineering firm.
2. A payment clause that obligates the contractor to take one of the two following actions within seven days after receipt of amounts paid to the contractor by the state agency or local government for work performed by the subcontractor under that contract:
a. Pay the subcontractor for the proportionate share of the total payment received from the agency attributable to the work performed by the subcontractor under that contract; or
b. Notify the agency and subcontractor, in writing, of his intention to withhold all or a part of the subcontractor's payment with the reason for nonpayment.
3. A payment clause that requires (i) individual contractors to provide their social security numbers and (ii) proprietorships, partnerships, and corporations to provide their federal employer identification numbers.
4. An interest clause that obligates the contractor to pay interest to the subcontractor on all amounts owed by the contractor that remain unpaid after seven days following receipt by the contractor of payment from the state agency or agency of local government for work performed by the subcontractor under that contract, except for amounts withheld as allowed in subdivision 2.
5. An interest rate clause stating, "Unless otherwise provided under the terms of this contract, interest shall accrue at the rate of one percent per month."
Any such contract awarded shall further require the contractor to include in each of its subcontracts a provision requiring each subcontractor to include or otherwise be subject to the same payment and interest requirements with respect to each lower-tier subcontractor.
A contractor's obligation to pay an interest charge to a subcontractor pursuant to the payment clause in this section shall not be construed to be an obligation of the state agency or agency of local government. A contract modification shall not be made for the purpose of providing reimbursement for the interest charge. A cost reimbursement claim shall not include any amount for reimbursement for the interest charge.
1990, c. 824, § 11-62.11; 1992, c. 110; 2001, c. 844; 2022, c. 727; 2023, cc. 675, 676.
§ 2.2-4355. Interest penalty; exceptions.A. Interest shall accrue, at the rate determined pursuant to subsection B, on all amounts owed by a state agency to a vendor that remain unpaid after seven days following the payment date. However, nothing in this section shall affect any contract providing for a different rate of interest, or for the payment of interest in a different manner.
B. The rate of interest charged a state agency pursuant to subsection A shall be the base rate on corporate loans (prime rate) at large United States money center commercial banks as reported daily in the publication entitled The Wall Street Journal. Whenever a split prime rate is published, the lower of the two rates shall be used. However, in no event shall the rate of interest charged exceed the rate of interest established pursuant to § 58.1-1812.
C. Notwithstanding subsection A, no interest penalty shall be charged when payment is delayed because of disagreement between a state agency and a vendor regarding the quantity, quality or time of delivery of goods or services or the accuracy of any invoice received for the goods or services. The exception from the interest penalty provided by this subsection shall apply only to that portion of a delayed payment that is actually the subject of the disagreement and shall apply only for the duration of the disagreement.
D. This section shall not apply to § 2.2-4333 pertaining to retainage on construction contracts, during the period of time prior to the date the final payment is due. Nothing contained herein shall prevent a contractor from receiving interest on such funds under an approved escrow agreement.
E. Notwithstanding subsection A, no interest penalty shall be paid to any debtor on any payment, or portion thereof, withheld pursuant to the Comptroller's Debt Setoff Program, as authorized by the Virginia Debt Collection Act (§ 2.2-4800 et seq.), commencing with the date the payment is withheld. If, as a result of an error, a payment or portion thereof is withheld, and it is determined that at the time of setoff no debt was owed to the Commonwealth, then interest shall accrue at the rate determined pursuant to subsection B on amounts withheld that remain unpaid after seven days following the payment date.
1984, c. 736, § 11-62.5; 1985, c. 101; 1992, c. 75; 2001, c. 844.
§ 2.2-4356. Comptroller to file annual report.The Comptroller shall file an annual report with the Governor, the Senate Committee on Finance and Appropriations, the House Committees on Finance and Appropriations on November 1 for the preceding fiscal year including (i) the number and dollar amounts of late payments by departments, institutions and agencies, (ii) the total amount of interest paid and (iii) specific steps being taken to reduce the incidence of late payments.