Part III. General Operating Requirements
9VAC25-580-80. Spill and overfill control.
A. Owners and operators must ensure that releases due to spilling or overfilling do not occur. The owner and operator must ensure that the volume available in the tank is greater than the volume of product to be transferred to the tank before the transfer is made and that the transfer operation is monitored constantly to prevent overfilling and spilling.
NOTE: The transfer procedures described in National Fire Protection Association Standard 385 Standard for Tank Vehicles for Flammable and Combustible Liquids or American Petroleum Institute Recommended Practice 1007, Loading and Unloading of MC 306/DOT 406 Cargo Tank Motor Vehicles may be used to comply with this subsection. Further guidance on spill and overfill prevention appears in American Petroleum Institute, Recommended Practice 1621, Bulk Liquid Stock Control at Retail Outlets.
B. The owner and operator must report, investigate, and clean up any spills and overfills in accordance with 9VAC25-580-220.
Statutory Authority
§§ 62.1-44.15 and 62.1-44.34:9 of the Code of Virginia; 42 USC § 6901 et seq.; 40 CFR Parts 280 and 281.
Historical Notes
Derived from VR680-13-02 § 3.1, eff. October 25, 1989; amended, Virginia Register Volume 34, Issue 1, eff. January 1, 2018.
9VAC25-580-82. Periodic testing of spill prevention equipment and containment sumps used for interstitial monitoring of piping and periodic inspection of overfill prevention equipment.
A. Owners and operators of UST systems with spill and overfill prevention equipment and containment sumps used for interstitial monitoring of piping must meet these requirements to ensure the equipment is operating properly and will prevent releases to the environment:
1. Spill prevention equipment (such as a catchment basin, spill bucket, or other spill containment device) and containment sumps used for interstitial monitoring of piping must prevent releases to the environment by meeting one of the following:
a. The equipment is double walled and the integrity of both walls is periodically monitored as described in 9VAC25-580-85 A 1 a (1) at a frequency not less than the frequency of the walkthrough inspections described in 9VAC25-580-85. Within 30 days of discontinuing periodic monitoring under this subdivision, owners and operators must conduct a test in accordance with subdivision A 1 b of this section and begin meeting the requirements of that subdivision; or
b. The spill prevention equipment and containment sumps used for interstitial monitoring of piping are tested at least once every three years to ensure the equipment is liquid tight by using vacuum, pressure, or liquid testing in accordance with one of the following criteria:
(1) Requirements developed by the manufacturer (Note: Owners and operators may use this option only if the manufacturer has developed requirements);
(2) Code of practice developed by a nationally recognized association or independent testing laboratory; or
(3) Requirements determined by the department to be no less protective of human health and the environment than the requirements listed in subdivisions A 1 b (1) and (2) of this section.
2. Overfill prevention equipment must be inspected at least once every three years. At a minimum, the inspection must ensure that overfill prevention equipment is set to activate at the correct level specified in subdivision 3 of 9VAC25-580-50 and will activate when regulated substance reaches that level. Inspections must be conducted in accordance with one of the criteria in subdivisions 1 b (1), (2), or (3) of this subsection.
NOTE: The following code of practice may be used to comply with subdivisions A 1 b and A 2 of this section: Petroleum Equipment Institute Publication RP 1200, Recommended Practices for the Testing and Verification of Spill, Overfill, Leak Detection and Secondary Containment Equipment at UST Facilities.
B. Owners and operators must begin meeting these requirements as follows:
1. For UST systems in use before January 1, 2018, the initial spill prevention equipment test, containment sump test, and overfill prevention equipment inspection must be conducted not later than January 1, 2021.
2. For UST systems brought into use on or after January 1, 2018, these requirements apply at installation.
C. Owners and operators must maintain records as follows in accordance with 9VAC25-580-120 for spill prevention equipment, containment sumps used for interstitial monitoring of piping, and overfill prevention equipment:
1. All records of testing or inspection must be maintained for three years; and
2. For spill prevention equipment and containment sumps used for interstitial monitoring of piping not tested every three years, documentation showing that the prevention equipment is double walled and the integrity of both walls is periodically monitored must be maintained for as long as the equipment is periodically monitored.
Statutory Authority
§§ 62.1-44.15 and 62.1-44.34:9 of the Code of Virginia; 42 USC § 6901 et seq.; 40 CFR Parts 280 and 281.
Historical Notes
Derived from Virginia Register Volume 34, Issue 1, eff. January 1, 2018; Errata, 34:4 VA.R. 503 October 16, 2017; amended, Virginia Register Volume 39, Issue 5, eff. November 23, 2022.
9VAC25-580-85. Periodic operation and maintenance walkthrough inspections.
A. To properly operate and maintain UST systems, not later than January 1, 2021, owners and operators must meet one of the following:
1. Conduct a walkthrough inspection that, at a minimum, checks the following equipment as specified below:
a. Every 30 days (Exception: spill prevention equipment at UST systems receiving deliveries at intervals greater than every 30 days may be checked prior to each delivery):
(1) Spill prevention equipment – visually check for damage; remove liquid or debris; check for and remove obstructions in the fill pipe; check the fill cap to make sure it is securely on the fill pipe; and, for double walled spill prevention equipment with interstitial monitoring, check for a leak in the interstitial area; and
(2) Release detection equipment – check to make sure the release detection equipment is operating with no alarms or other unusual operating conditions present and ensure records of release detection testing are reviewed and current; and
b. Annually:
(1) Containment sumps – visually check for damage, leaks to the containment area, or releases to the environment; remove liquid (in contained sumps) or debris; and, for double walled sumps with interstitial monitoring, check for a leak in the interstitial area; and
(2) Handheld release detection equipment – check devices such as tank gauge sticks or groundwater bailers for operability and serviceability;
2. Conduct operation and maintenance walkthrough inspections according to a standard code of practice developed by a nationally recognized association or independent testing laboratory that checks equipment comparable to subdivision 1 of this subsection; or
3. Conduct operation and maintenance walkthrough inspections according to a protocol developed by the department that checks equipment comparable to subdivision 1 of this subsection.
B. Owners and operators must maintain records (in accordance with 9VAC25-580-120) of operation and maintenance walkthrough inspections for one year. Records must include a list of each area checked, whether each area checked was acceptable or needed action taken, a description of actions taken to correct an issue, and delivery records if spill prevention equipment is checked less frequently than every 30 days due to infrequent deliveries.
NOTE: The following code of practice may be used to comply with subdivision A 2 of this section: Petroleum Equipment Institute Recommended Practice RP 900, Recommended Practices for the Inspection and Maintenance of UST Systems.
Statutory Authority
§§ 62.1-44.15 and 62.1-44.34:9 of the Code of Virginia; 42 USC § 6901 et seq.; 40 CFR Parts 280 and 281.
Historical Notes
Derived from Virginia Register Volume 34, Issue 1, eff. January 1, 2018; Errata, 34:4 VA.R. 503 October 16, 2017; amended, Virginia Register Volume 39, Issue 5, eff. November 23, 2022.
9VAC25-580-90. Operation and maintenance of corrosion protection.
All owners and operators of metal UST systems with corrosion protection must comply with the following requirements to ensure that releases due to corrosion are prevented until the UST system is permanently closed or undergoes a change-in-service pursuant to 9VAC25-580-320:
1. All corrosion protection systems must be operated and maintained to continuously provide corrosion protection to the metal components of that portion of the tank and piping that routinely contain regulated substances and are in contact with the ground.
2. All UST systems equipped with cathodic protection systems must be inspected for proper operation by a qualified cathodic protection tester in accordance with the following requirements:
a. Frequency. All cathodic protection systems must be tested within six months of installation and at least every three years thereafter; and
b. Inspection criteria. The criteria that are used to determine that cathodic protection is adequate as required by this section must be in accordance with a code of practice developed by a nationally recognized association.
NOTE: The following codes of practice may be used to comply with subdivision 2 of this section:
(1) NACE International Test Method TM0101, Measurement Techniques Related to Criteria for Cathodic Protection of Underground Storage Tank Systems;
(2) NACE International Test Method TM0497, Measurement Techniques Related to Criteria for Cathodic Protection on Underground or Submerged Metallic Piping Systems;
(3) Steel Tank Institute Recommended Practice R051, Cathodic Protection Testing Procedures for STI-P3® USTs;
(4) NACE International Standard Practice SP0285, External Control of Underground Storage Tank Systems by Cathodic Protection; or
(5) NACE International Standard Practice SP0169, Control of External Corrosion on Underground or Submerged Metallic Piping Systems.
3. UST systems with impressed current cathodic protection systems must also be inspected every 60 days to ensure the equipment is running properly. These systems only provide the necessary corrosion protection when in continuous operation. Such equipment shall be installed so that it cannot be inadvertently shut off.
4. For UST systems using cathodic protection, records of the operation of the cathodic protection must be maintained (in accordance with 9VAC25-580-120) to demonstrate compliance with the performance standards in this section. These records must provide the following:
a. The results of the last three inspections required in subdivision 3 of this section; and
b. The results of testing from the last two inspections required in subdivision 2 of this section.
Statutory Authority
§§ 62.1-44.15 and 62.1-44.34:9 of the Code of Virginia; 42 USC § 6901 et seq.; 40 CFR Parts 280 and 281.
Historical Notes
Derived from VR680-13-02 § 3.2, eff. October 25, 1989; amended, Virginia Register Volume 34, Issue 1, eff. January 1, 2018.
9VAC25-580-100. Compatibility.
A. Owners and operators must use an UST system made of or lined with materials that are compatible with the substance stored in the UST system.
B. Owners and operators must notify the department at least 30 days prior to switching to a regulated substance containing greater than 10% ethanol, greater than 20% biodiesel, or any other regulated substance identified by the department. In addition, owners and operators with UST systems storing these regulated substances must meet one of the following:
1. Demonstrate compatibility of the UST system, including the tank, piping, containment sumps, pumping equipment, release detection equipment, spill equipment, and overfill equipment. Owners and operators may demonstrate compatibility of the UST system by using one of the following options:
a. Certification or listing of UST system equipment or components by a nationally recognized, independent testing laboratory for use with the regulated substance stored; or
b. Equipment or component manufacturer approval. The manufacturer's approval must be in writing, indicate an affirmative statement of compatibility, specify the range of biofuel blends the equipment or component is compatible with, and be from the equipment or component manufacturer; or
2. Use another option determined by the department to be no less protective of human health and the environment than the options listed in subdivision 1 of this subsection.
C. Owners and operators must maintain records in accordance with subdivision 2 of 9VAC25-580-120 documenting compliance with subsection B of this section for as long as the UST system is used to store the regulated substance.
NOTE: The following code of practice may be useful in complying with this section:
American Petroleum Institute Recommended Practice 1626, Storing and Handling Ethanol and Gasoline-Ethanol Blends at Distribution Terminals and Filling Stations.
Statutory Authority
§§ 62.1-44.15 and 62.1-44.34:9 of the Code of Virginia; 42 USC § 6901 et seq.; 40 CFR Parts 280 and 281.
Historical Notes
Derived from VR680-13-02 § 3.3, eff. October 25, 1989; amended, Virginia Register Volume 34, Issue 1, eff. January 1, 2018; Volume 39, Issue 5, eff. November 23, 2022.
9VAC25-580-110. Repairs allowed.
Owners and operators must obtain a permit and the required inspections in accordance with the provisions of the Virginia Uniform Statewide Building Code (§ 36-97 et seq. of the Code of Virginia).
A permit from the building official must be obtained prior to repairing any UST system. No repaired UST system shall be placed into use unless and until the system is inspected in accordance with the provisions of the Virginia Uniform Statewide Building Code (§ 36-97 et seq. of the Code of Virginia).
In the case of state-owned facilities the Department of General Services shall function as the building official in accordance with § 36-98.1 of the Code of Virginia.
In the case of federal facilities the building official must be contacted. Owners and operators must obtain a permit and the required inspections in accordance with the provisions of the Virginia Uniform Statewide Building Code (§ 36-97 et seq. of the Code of Virginia).
Owners and operators of UST systems must ensure that repairs will prevent releases due to structural failure or corrosion as long as the UST system is used to store regulated substances. The repairs must meet the following requirements:
1. Repairs to UST systems must be properly conducted in accordance with a code of practice developed by a nationally recognized association or an independent testing laboratory.
NOTE: The following codes of practice may be used to comply with subdivision 1 of this section:
a. National Fire Protection Association Standard 30, Flammable and Combustible Liquids Code;
b. American Petroleum Institute Recommended Practice RP 2200, Repairing Crude Oil, Liquefied Petroleum Gas, and Product Pipelines;
c. American Petroleum Institute Recommended Practice RP 1631, Interior Lining and Periodic Inspection of Underground Storage Tanks;
d. National Fire Protection Association Standard 326, Standard for the Safeguarding of Tanks and Containers for Entry, Cleaning, or Repair;
e. National Leak Prevention Association Standard 631, Chapter A, Entry, Cleaning, Interior Inspection, Repair, and Lining of Underground Storage Tanks;
f. Steel Tank Institute Recommended Practice R972, Recommended Practice for the Addition of Supplemental Anodes to STI-P3® Tanks;
g. NACE International Standard Practice SP 0285, External Control of Underground Storage Tank Systems by Cathodic Protection; or
h. Fiberglass Tank and Pipe Institute Recommended Practice T-95-02, Remanufacturing of Fiberglass Reinforced Plastic (FRP) Underground Storage Tanks.
2. Repairs to fiberglass-reinforced plastic tanks may be made by the manufacturer's authorized representatives or in accordance with a code of practice developed by a nationally recognized association or an independent testing laboratory.
3. Metal pipe sections and fittings that have released product as a result of corrosion or other damage must be replaced. Noncorrodible pipes and fittings may be repaired in accordance with the manufacturer's specifications.
4. Repairs to secondary containment areas of tanks and piping used for interstitial monitoring and to containment sumps used for interstitial monitoring of piping must have the secondary containment tested for tightness according to the manufacturer's instructions, a code of practice developed by a nationally recognized association or independent testing laboratory, or according to requirements established by the department within 30 days following the date of completion of the repair.
5. All other repairs to tanks and piping must be tightness tested in accordance with subdivision 3 of 9VAC25-580-160 and subdivision 2 of 9VAC25-580-170 within 30 days following the date of the completion of the repair except as provided below:
a. The repaired tank is internally inspected in accordance with a code of practice developed by a nationally recognized association or an independent testing laboratory;
b. The repaired portion of the UST system is monitored monthly for releases in accordance with a method specified in subdivisions 4 through 9 of 9VAC25-580-160; or
c. Another test method is used that is determined by the department to be no less protective of human health and the environment than those listed in subdivisions a and b of this subdivision 5.
NOTE: The following codes of practice may be used to comply with subdivisions 4 and 5 of this section:
(1) Steel Tank Institute Recommended Practice R012, Recommended Practice for Interstitial Tightness Testing of Existing Underground Double Wall Steel Tanks; or
(2) Fiberglass Tank and Pipe Institute Protocol, Field Test Protocol for Testing the Annular Space of Installed Underground Fiberglass Double and Triple-Wall Tanks With Dry Annular Space.
(3) Petroleum Equipment Institute Recommended Practice RP1200, Recommended Practices for the Testing and Verification of Spill, Overfill, Leak Detection and Secondary Containment Equipment at UST Facilities.
6. Within six months following the repair of any cathodically protected UST system, the cathodic protection system must be tested in accordance with subdivisions 2 and 3 of 9VAC25-580-90 to ensure that it is operating properly.
7. Within 30 days following any repair to spill or overflow prevention equipment, the repaired spill or overflow prevention equipment must be tested or inspected as appropriate, in accordance with 9VAC25-580-82 to ensure it is operating properly.
8. UST system owners and operators must maintain records in accordance with 9VAC25-580-120 of each repair until the UST system is permanently closed or undergoes a change-in-service pursuant to 9VAC25-580-320.
Statutory Authority
§§ 62.1-44.15 and 62.1-44.34:9 of the Code of Virginia; 42 USC § 6901 et seq.; 40 CFR Parts 280 and 281.
Historical Notes
Derived from VR680-13-02 § 3.4, eff. October 25, 1989; amended, Virginia Register Volume 34, Issue 1, eff. January 1, 2018; Volume 39, Issue 5, eff. November 23, 2022.
9VAC25-580-120. Reporting and recordkeeping.
Owners and operators of UST systems must cooperate fully with inspections, monitoring and testing conducted by the department, as well as requests for document submission, testing, and monitoring by the owner or operator pursuant to § 9005 of Subtitle I of the Solid Waste Disposal Act, as amended.
1. Reporting. Owners and operators must submit the following information to the department:
a. Notification for all UST systems (9VAC25-580-70), which includes certification of installation for new UST systems (subdivision 5 of 9VAC25-580-50) and notification when any person assumes ownership of an UST system (9VAC25-580-70);
b. Notification prior to UST systems switching to certain regulated substances (subsection B of 9VAC25-580-100);
c. Reports of all releases including suspected releases (9VAC25-580-190), spills and overfills (9VAC25-580-220), and confirmed releases (9VAC25-580-240);
d. Corrective actions planned or taken including initial abatement measures (9VAC25-580-250), site characterization (9VAC25-580-260), free product removal (9VAC25-580-270), and corrective action plan (9VAC25-580-280); and
e. An amended notification form must be submitted within 30 days after permanent closure or change-in-service (9VAC25-580-320).
2. Recordkeeping. Owners and operators must maintain the following information:
a. Documentation of operation of corrosion protection equipment (subdivision 4 of 9VAC25-580-90);
b. Documentation of compatibility for UST systems (subsection C of 9VAC25-580-100);
c. Documentation of UST system repairs (subdivision 8 of 9VAC25-580-110);
d. Documentation of compliance and applicable installation records for spill and overfill prevention equipment and containment sumps used for interstitial monitoring of piping (subsection C of 9VAC25-580-82);
e. Documentation of periodic walkthrough inspections (subsection B of 9VAC25-580-85);
f. Documentation of compliance with release detection requirements (9VAC25-580-180);
g. Results of the site investigation conducted at permanent closure (9VAC25-580-350); and
h. Documentation of operator training required by 9VAC25-580-125, including verification of training for current Class A, Class B, and Class C operators, and current list of operators and written instructions or procedures for Class C operators (9VAC25-580-125).
3. Availability and maintenance of records. Owners and operators must keep the records required either:
a. At the UST site and immediately available for inspection by the department; or
b. At a readily available alternative site and be provided for inspection to the department upon request.
In the case of permanent closure records required under 9VAC25-580-350, owners and operators are also provided with the additional alternative of mailing closure records to the department if they cannot be kept at the site or an alternative site as indicated above.
Statutory Authority
§§ 62.1-44.15 and 62.1-44.34:9 of the Code of Virginia; 42 USC § 6901 et seq.; 40 CFR Parts 280 and 281.
Historical Notes
Derived from VR680-13-02 § 3.5, eff. October 25, 1989; amended, Virginia Register Volume 26, Issue 25, eff. September 15, 2010; Volume 34, Issue 1, eff. January 1, 2018; Volume 39, Issue 5, eff. November 23, 2022.
9VAC25-580-125. Operator training.
A. Definitions.
1. For purposes of this section, "Class A operator" means an operator who has primary responsibility to operate and maintain the underground storage tank system and facility. The Class A operator's responsibilities include managing resources and personnel, such as establishing work assignments, to achieve and maintain compliance with regulatory requirements. In general, Class A operators focus on the broader aspects of the underground storage tank statutory and regulatory requirements and standards necessary to properly operate and maintain the underground storage tank system and facility.
2. For purposes of this section, "Class B operator" means an operator who implements applicable underground storage tank regulatory requirements and standards in the field or at the underground storage tank facility. A Class B operator oversees and implements the day-to-day aspects of operations, maintenance, and recordkeeping for the underground storage tanks at one or more facilities.
3. For purposes of this section, "Class C operator" means the person responsible for responding to alarms or other indications of emergencies caused by spills or releases from underground storage tank systems and equipment failures. A Class C operator, generally, is the first line of response to events indicating emergency conditions.
B. Requirements for trained operators.
1. Owners and operators of UST systems shall designate Class A, Class B, and Class C operators for each UST system or facility that has underground storage tanks.
a. A person may be designated for more than one class of operator.
b. Any person designated for more than one class of operator shall successfully complete the required training under subsection C of this section for each operator class for which he is designated.
c. Persons trained in accordance with subsection C of this section may perform operator duties consistent with their training when employed or contracted by the tank owner or operator to perform these functions.
2. Class A operators shall be familiar with training requirements for each class of operator and may provide required training for Class C operators.
3. Class B operators shall be familiar with Class B and Class C operator responsibilities and may provide training for Class C operators.
4. Trained operators shall be readily available to respond to suspected/confirmed releases, other unusual operating conditions and equipment shut-offs or failures.
a. The Class A or Class B operator shall be available for immediate telephone consultation when an UST facility is in operation. A Class A or Class B operator shall be able to be onsite at the facility within a reasonable time to perform necessary functions.
b. For manned facilities, a Class C operator shall be onsite whenever the UST facility is in operation. After September 15, 2010, written instructions or procedures shall be maintained and visible at manned UST facilities for persons performing duties of the Class C operator to follow and to provide notification necessary in the event of emergency conditions.
c. For unmanned facilities, a Class C operator shall be available for immediate telephone consultation and shall be able to be onsite within a reasonable time to perform necessary functions. Emergency contact information shall be prominently displayed at the site. After September 15, 2010, written instructions or procedures shall be maintained and visible at unmanned UST facilities for persons performing duties of the Class C operator to follow and to provide notification necessary in the event of emergency conditions.
C. Required training.
1. Class A operators shall successfully complete a training course approved by the department that includes a general knowledge of UST system requirements. Training shall provide information that should enable the operator to make informed decisions regarding compliance and ensuring that appropriate persons are fulfilling operation, maintenance, and recordkeeping requirements and standards of this chapter and/or federal underground storage tank requirements in 40 CFR Part 280 (relating to technical standards and corrective action requirements for owners and operators of underground storage tanks (UST)), including, at a minimum, the following:
a. Spill and overfill prevention;
b. Release detection and related reporting requirements;
c. Corrosion protection;
d. Emergency response;
e. Product and equipment compatibility;
f. Financial responsibility;
g. Notification and storage tank registration requirements;
h. Temporary and permanent closure requirements; and
i. Class B and Class C operator training requirements.
2. Class B operators shall successfully complete a training course approved by the department that includes an in-depth understanding of operation and maintenance aspects of UST systems and related regulatory requirements. Training shall provide specific information on the components of UST systems, materials of construction, methods of release detection and release prevention applied to UST systems and components. Training shall address operation and maintenance requirements of this chapter and/or federal underground storage tank requirements in 40 CFR Part 280, including, at a minimum, the following:
a. Spill and overfill prevention;
b. Release detection and related reporting requirements;
c. Corrosion protection and related testing;
d. Emergency response;
e. Product and equipment compatibility;
f. Reporting and recordkeeping requirements; and
g. Class C operator training requirements.
3. Class C operators. At a minimum, training provided by the tank owner or Class A or Class B operator shall enable the Class C operator to take action in response to emergencies caused by spills or releases and alarms from an underground storage tank. Training shall include written instructions or procedures for the Class C operator to follow and to provide notification necessary in the event of emergency conditions.
4. Successful completion for Class A and Class B operators means completion of the entire training course and demonstration of knowledge of the course material as follows:
a. Receipt of a passing grade (a score of 80% or better) on an examination of material presented in the training course, or demonstration through practical (hands-on) application to the trainer of operation and maintenance checks of underground storage tank equipment, including performance of release detection at the UST facility, at the conclusion of onsite training; and
b. Receipt of a training certificate by an approved trainer upon verification of successful completion of training under this section.
5. Reciprocity. The department may also recognize successful completion of Class A and Class B operator training on regulatory standards consistent with 40 CFR Part 280, which is recognized by other state or implementing agencies and which is approved by EPA as meeting operator training grant guidelines published by EPA.
6. The tank owner and operator shall incur the costs of the training.
D. Timing of training.
1. An owner and operator shall ensure that Class A, Class B and Class C operators are trained as soon as practicable after September 15, 2010, contingent upon availability of approved training providers, but not later than August 8, 2012.
2. When a Class A or Class B operator is replaced after August 8, 2012, a new operator shall be trained within 60 days of assuming duties for that class of operator.
3. Class C operators shall be trained before assuming duties of a Class C operator. After September 15, 2010, written instructions or procedures shall be provided to Class C operators to follow and to provide notification necessary in the event of emergency conditions. Class C operators shall be briefed on these instructions or procedures at least annually (every 12 months), which may be concurrent with annual safety training required under Occupational Safety and Health Administration, 29 CFR Part 1910 (relating to Occupational Safety and Health Standards).
E. Retraining.
1. Owners and operators of UST systems shall ensure that Class A and B operators in accordance with subsection C of this section are retrained if the department determines that the UST system is out of compliance with the requirements of 9VAC25-580-30 through 9VAC25-580-190. At a minimum, Class A and Class B operators shall successfully complete retraining in the areas identified as out of compliance.
2. Class A and B operators shall complete training pursuant to this subsection no later than 90 days from the date the department identifies the noncompliance.
F. Documentation.
1. Owners and operators of underground storage tank facilities shall prepare and maintain a list of designated Class A, Class B, and Class C operators. The list shall represent the current Class A, Class B, and Class C operators for the UST facility and shall include:
a. The name of each operator, class of operation trained for, and the date each operator successfully completed initial training and refresher training, if any.
b. For Class A and Class B operators that are not permanently onsite or assigned to more than one facility, telephone numbers to contact the operators.
2. A copy of the certificates of training for Class A and Class B operators shall be on file as long as each operator serves in that capacity at the facility or three years, whichever is longer, and readily available, and a copy of the facility list of Class A, Class B, and Class C operators and Class C operator instructions or procedures shall be kept onsite and immediately available for manned UST facilities and readily available for unmanned facilities (see subdivision 2 h of 9VAC25-580-120 relating to reporting and recordkeeping).
3. Class C operator and owner contact information, including names and telephone numbers, and any emergency information shall be conspicuously posted at unmanned facilities.
Statutory Authority
§§ 62.1-44.15 and 62.1-44.34:9 of the Code of Virginia; 42 USC § 6901 et seq.; 40 CFR Parts 280 and 281.
Historical Notes
Derived from VR680-13-02 § 1.2, eff. October 25, 1989; amended, Virginia Register Volume 26, Issue 25, eff. September 15, 2010; Volume 34, Issue 1, eff. January 1, 2018; Volume 39, Issue 5, eff. November 23, 2022.