Title 56. Public Service Companies
Chapter 10. Heat, Light, Power, Water and Other Utility Companies Generally
Article 3. Powers of Commission in Relation to Service.
§ 56-246. Tests and equipment therefor.The Commission may purchase such materials, apparatus and standard measuring instruments for such examinations and tests as it may deem necessary, and may provide for the examinations and testing of the service or any part thereof of any public utility in this Commonwealth at such time and under such circumstances as the Commission may deem best.
Code 1919, § 4069.
§ 56-247. Commission may change regulations, measurements, practices, services, or acts.If upon investigation it shall be found that any regulation, measurement, practice, act or service of any public utility complained of is unjust, unreasonable, insufficient, preferential, unjustly discriminatory or otherwise in violation of law or if it be found that any service is inadequate or that any reasonable service cannot be obtained, the Commission may substitute therefor such other regulations, measurements, practices, service or acts and make such order respecting, and such changes in, such regulations, measurements, practices, service or acts as shall be just and reasonable.
The Commission shall investigate the promotional allowances and practices of public utilities and shall take such action as such investigation may indicate to be in the public interest.
Code 1919, § 4072; 1966, c. 552.
§ 56-247.1. Commission to require public utilities to follow certain procedures.A. The Commission shall require that public utilities adhere to the following procedures for services not found to be competitive:
1. Every public utility shall provide its residential customers one full billing period to pay for one month's local or basic services, before initiating any proceeding against a residential customer for nonpayment of local service.
2. Pay the residential customer a fair rate of interest as determined by the Commission on money deposited and return the deposit with the interest after not more than one year of satisfactory credit has been established.
3. Every public utility shall establish customer complaint procedures that will ensure prompt and effective handling of all customer inquiries, service requests, and complaints. Such procedure shall be approved by the Commission before its implementation and it shall be distributed to its residential customers. The utility shall disclose to the customer that the Commission is the responsible regulatory agency and that the customer may contact the Commission on regulatory matters and provide the customer with the contact information for the Commission.
4. No electric or gas utility shall terminate a customer's service without 10 days' notice by mail to the customer.
5. No public utility shall terminate the residential service of a customer for such customer's nonpayment of basic nonresidential services as defined by its terms and conditions on file with the Virginia State Corporation Commission.
6. A public utility providing water service shall not terminate service for nonpayment until it first sends the customer written notice by mail 10 days in advance of making the termination but, in no event, shall it terminate the customer's service until 20 days after the customer's bill has become due. Any such notice shall also include contact information for the customer's use in contacting the public utility regarding the notice.
7. Any electric utility formed under or subject to Chapter 9.1 (§ 56-231.15 et seq.) may install and operate, upon a customer's request and pursuant to an appropriate tariff for any type or classification of service, a prepaid metering equipment and system that is configured to terminate electric service immediately and automatically when the customer has incurred charges for electric service equal to the customer's prepayments for such service. Subdivisions 1, 2, 4, and 5 shall not apply to services provided pursuant to electric service provided on a prepaid basis by a prepaid metering equipment and system pursuant to this subsection. Such tariffs shall be filed with the Commission for its review and determination that the tariff is not contrary to the public interest.
8. No electric utility shall terminate the residential service of a customer for such customer's nonpayment for metered services when the electric utility believes that the customer is receiving or has received electric utility services for which the customer was not properly billed as the result of tampering with the electric utility's meter in a manner that prevented the meter from accurately recording usage, until the electric utility has complied with the procedure set forth in subsection C. However, the requirement that the electric utility comply with the procedure set forth in subsection C before terminating service shall not apply if (i) the condition of a customer's wiring, equipment, or appliances is either unsafe or unsuitable for receiving the electric utility service; (ii) the customer's use of the electric utility service or equipment interferes with or may be detrimental to the electric utility's facilities or to the provision of electric utility service by the electric utility to any other customer; (iii) a tamper-evident meter seal securing the meter is broken, damaged, or missing; (iv) electric service is furnished over a line that is not owned or leased by the electric utility and the line is either not in a safe and suitable condition or is inadequate to receive electric utility service; (v) emergency repairs or alterations are needed; (vi) there are unavoidable shortages or interruptions in a supply of utility service; (vii) the electric utility is acting upon orders from an authority having jurisdiction; or (viii) the actions taken are to preserve life or property, or to avoid or abate utility or fire hazard.
B. Any and all Commission rules and regulations concerning the denial of telephone service for nonpayment of such service shall not apply to services found to be competitive.
C. If an electric utility believes that a customer is receiving or has received electric utility services for which the customer was not properly billed as the result of tampering with the electric utility's meter in a manner that prevented the meter from accurately recording usage, the electric utility shall (i) retrieve the meter from the customer's premises, which may be done without providing prior notice to the customer; (ii) immediately replace it with a new meter; and (iii) determine whether the meter has been tampered with. Within 60 days after any such determination of meter tampering has been made, the electric utility shall provide evidence of such tampering to the customer. If, after determining the meter has been tampered with, the electric utility seeks payment for electric utility services not properly billed, the electric utility shall provide the customer with an invoice with a reasonable and final estimate of the amount owed by the customer as a result of the meter's failure to accurately record the customer's usage. The invoice shall explain the electric utility's calculation of the estimated amount owed as a result of any suspected failure. The electric utility shall provide the customer one full billing period to pay the amount billed in such invoice before initiating any proceeding against the customer for nonpayment. During such billing period, the customer may submit an informal complaint to the Commission disputing the amount sought by the utility. The customer may commence a formal proceeding after the informal complaint process has been exhausted in accordance with Commission regulations.
1976, c. 738; 1977, c. 59; 1980, c. 415; 2010, c. 320; 2011, cc. 500, 738, 740; 2020, c. 668.
§ 56-248. Commission to prescribe standard units of products or service.The Commission shall ascertain and prescribe for each kind of public utility suitable standard commercial units of products or service. This section shall not apply to telephone companies.
Code 1919, § 4070; 2011, cc. 738, 740.
§ 56-248.1. Commission to monitor fuel prices and utility fuel purchases; fuel price index.A. The Commission shall monitor all fuel purchases, transportation costs, and contracts for such purchases of a utility to ascertain that all feasible economies are being utilized. Subject to the provisions of § 56-234, the Commission shall allow natural gas utilities to include in their fuel portfolios supplemental or substitute forms of gas sources that meet the natural gas utility's pipeline quality gas standards and that reduce the emissions intensity of its fuel portfolio. A natural gas utility shall procure supplemental or substitute forms of gas sources utilizing standard industry practices and shall report to the Commission annually the imputed reduction in carbon dioxide equivalent resulting from such purchasing practices.
B. As used in this section:
"Biogas" means a mixture of hydrocarbons that is a gas at 60 degrees Fahrenheit and one atmosphere of pressure that is produced through the anaerobic digestion or thermal conversion of organic matter.
"Low-emission natural gas" means natural gas produced from a geologic source that has a methane intensity of 0.20 or less (i) as reported under a protocol approved by the federal Environmental Protection Agency's Gas STAR Methane Challenge, (ii) as certified by the United Nations Environment Programme's Oil and Gas Methane Partnership 2.0, or (iii) as validated under a Qualified Attribute Commodities Platform.
"Methane intensity" means the methane emissions assigned to natural gas on an energy basis divided by the total methane content of produced natural gas.
"Qualified Attribute Commodities Platform" means a trading mechanism for natural gas or natural gas attributes that are nonfinancial intangible commodities that represents, packages, and certifies the qualifying attributes of an amount of low-emission natural gas. A Qualified Attribute Commodities Platform provides validation by an independent third party, provides natural gas or natural gas attributes capable of bilateral or exchange contract trading pursuant to standardized contracts for physical delivery that reasonably eliminate validation risk, and provides transparency for audit and reporting purposes.
"Supplemental or substitute forms of gas sources" means (i) low-emission natural gas, (ii) biogas, or (iii) hydrogen.
C. In addition, the Commission shall establish a fuel price index in order to compare the prices paid for the various types of fuel by Virginia utilities with the average price of the various types of fuel paid by other public utilities at comparable geographic locations in the market.
D. This section shall not apply to telephone companies.
1976, c. 507; 1982, c. 107; 2011, cc. 738, 740; 2022, cc. 728, 759.
§ 56-249. Reports by utilities.The Commission, with or without an investigation, may require any public utility to furnish to it in such form, at such times, and in such detail as the Commission shall require, such accounts, reports and other information of whatsoever kind or character as it may deem proper and in such form and detail as it may prescribe, in order to show completely the entire operation of the public utility in furnishing the unit of its product or service to the public.
Code 1919, § 4070.
§ 56-249.1. Commission may require transfer of gas, water or electricity by one utility to another; compensation.The Commission may require a public utility to transfer to another public utility of like business, gas, water or electricity, whenever the public health, welfare or safety shall be found to so require; provided, however, that the transferring public utility shall be compensated, at a rate fixed by the Commission, for all such deliveries by the receiving public utility.
1975, c. 358.
§ 56-249.2. Certain records to be maintained.All public utilities doing business in the Commonwealth that file a rate of return statement shall, on and after January 1, 1977, or the beginning of the next fiscal year of the public utility after such date, maintain all records necessary to prepare and submit annually a rate of return statement reflecting that part of its total business under regulation of the Commission.
1976, c. 742; 1979, c. 617; 2011, cc. 738, 740.
§ 56-249.3. Certain electric utilities to file reports in relation to fuel transactions, fuel purchases, fuel adjustment clauses, etc.The Commission shall require that public electric utilities, owning and operating generating facilities, or privately owned utilities purchasing power at wholesale for retail sales within this State, file monthly with the Commission for its review such information as it may deem necessary, which may include the following:
1. The various types of fuels received such as coal, oil, nuclear fuel or natural gas;
2. The following information on fossil fuels:
a. The supplier of the fossil fuel, the cost in cents per MBTU of the fuel, with a notation of whether the fuel was contracted for, purchased on the spot market or purchased from an affiliate of the electric utility;
b. The quantities of the various types of fossil fuels received stated in tons of coal, barrels of oil, millions of cubic feet of natural gas;
c. The average BTU content per pound, gallon or cubic foot received, whichever is applicable;
d. The average sulfur and ash content, where applicable, of the fuel received;
3. Total demurrage charges incurred at each generating plant;
4. Total cost of transportation incurred at each generating plant;
5. The quantity of fuel consumed by each generation unit in the generating plant;
6. The average cost of the fossil and nuclear fuel in cents per MBTU's consumed at each plant with and without handling charges;
7. The monthly net heat rate expressed in BTU's per kilowatt-hour for each generating unit;
8. The kilowatt-hour output delivered into the system on a monthly basis;
9. The monthly net kilowatt-hour interchange; and
10. The monthly system kilowatt-hour sales.
1977, c. 125; 1979, c. 617.
§ 56-249.4. How reports shall be filed; reports open to public; rules and regulations.A. The information filed pursuant to § 56-249.3 shall be filed with the Commission in affidavit form within forty-five days following the close of the reference month.
B. All such information and reports filed pursuant to this section and § 56-249.3 shall be open to the public and available for inspection.
C. The Commission shall promulgate all rules and regulations necessary to implement this section and § 56-249.3.
1977, c. 125; 1982, c. 107.
§ 56-249.5. Repealed.Repealed by Acts 1979, c. 492.
§ 56-249.6. Recovery of fuel and purchased power costs.A. 1. Each electric utility that purchases fuel for the generation of electricity or purchases power and that was not, as of July 1, 1999, bound by a rate case settlement adopted by the Commission that extended in its application beyond January 1, 2002, shall submit to the Commission its estimate of fuel costs, including the cost of purchased power, for the 12-month period beginning on the date prescribed by the Commission. Upon investigation of such estimates and hearings in accordance with law, the Commission shall direct each company to place in effect tariff provisions designed to recover the fuel costs determined by the Commission to be appropriate for that period, adjusted for any over-recovery or under-recovery of fuel costs previously incurred.
2. The Commission shall continuously review fuel costs and if it finds that any utility described in subdivision A 1 is in an over-recovery position by more than five percent, or likely to be so, it may reduce the fuel cost tariffs to correct the over-recovery.
3. Beginning July 1, 2009, for all utilities described in subdivision A 1 and subsection B, if the Commission approves any increase in fuel factor charges pursuant to this section that would increase the total rates of the residential class of customers of any such utility by more than 20 percent, the Commission, within six months following the effective date of such increase, shall review fuel costs, and if the Commission finds that the utility is, or is likely to be, in an over-recovery position with respect to fuel costs for the 12-month period for which the increase in fuel factor charges was approved by more than five percent, it may reduce the utility's fuel cost tariffs to correct the over-recovery.
B. All fuel costs recovery tariff provisions in effect on January 1, 2004, for any electric utility that purchases fuel for the generation of electricity and that was, as of July 1, 1999, bound by a rate case settlement adopted by the Commission that extended in its application beyond January 1, 2002, shall remain in effect until the later of (i) July 1, 2007 or (ii) the establishment of tariff provisions under subsection C. Any such utility shall continue to report to the Commission annually its actual fuel costs, including the cost of purchased power.
C. Each electric utility described in subsection B shall submit annually to the Commission its estimate of fuel costs, including the cost of purchased power, for successive 12-month periods beginning on July 1, 2007, and each July 1 thereafter. Upon investigation of such estimates and hearings in accordance with law, the Commission shall direct each such utility to place in effect tariff provisions designed to recover the fuel costs determined by the Commission to be appropriate for such periods, adjusted for any over-recovery or under-recovery of fuel costs previously incurred; however, (i) no such adjustment for any over-recovery or under-recovery of fuel costs previously incurred shall be made for any period prior to July 1, 2007, and (ii) the Commission shall order that the deferral portion, if any, of the total increase in fuel tariffs for all classes as determined by the Commission to be appropriate for the 12-month period beginning July 1, 2007, above the fuel tariffs previously existing, shall be deferred without interest and recovered from all classes of customers as follows: (i) in the 12-month period beginning July 1, 2008, that part of the deferral portion of the increase in fuel tariffs that the Commission determines would increase the total rates of the residential class of customers of the utility by four percent over the level of such total rates in existence on June 30, 2008, shall be recovered; (ii) in the 12-month period beginning July 1, 2009, that part of the balance of the deferral portion of the increase in fuel tariffs, if any, that the Commission determines would increase the total rates of the residential class of customers of the utility by four percent over the level of such total rates in existence on June 30, 2009, shall be recovered; and (iii) in the 12-month period beginning July 1, 2010, the entire balance of the deferral portion of the increase in fuel tariffs, if any, shall be recovered. The "deferral portion of the increase in fuel tariffs" means the portion of such increase in fuel tariffs that exceeds the amount of such increase in fuel tariffs that the Commission determines would increase the total rates of the residential class of customers of the utility by more than four percent over the level of such total rates in existence on June 30, 2007.
D. In proceedings under subsections A and C:
1. Energy revenues associated with off-system sales of power shall be credited against fuel factor expenses in an amount equal to the total incremental fuel factor costs incurred in the production and delivery of such sales. In addition, 75 percent of the total annual margins from off-system sales shall be credited against fuel factor expenses; however, the Commission, upon application and after notice and opportunity for hearing, may require that a smaller percentage of such margins be so credited if it finds by clear and convincing evidence that such requirement is in the public interest. The remaining margins from off-system sales shall not be considered in the biennial reviews of electric utilities conducted pursuant to § 56-585.1. In the event such margins result in a net loss to the electric utility, (i) no charges shall be applied to fuel factor expenses and (ii) any such net losses shall not be considered in the biennial reviews of electric utilities conducted pursuant to § 56-585.1. For purposes of this subsection, "margins from off-system sales" shall mean the total revenues received from off-system sales transactions less the total incremental costs incurred; and
2. The Commission shall disallow recovery of any fuel costs that it finds without just cause to be the result of failure of the utility to make every reasonable effort to minimize fuel costs or any decision of the utility resulting in unreasonable fuel costs, giving due regard to reliability of service and the need to maintain reliable sources of supply, economical generation mix, generating experience of comparable facilities, and minimization of the total cost of providing service.
In any proceeding for the recovery of fuel costs under this subdivision in which the costs a utility seeks to recover include costs incurred under a natural gas capacity contract for a term of more than 10 years that procures more than 250,000 dekatherms per day that has not previously been subject to a review under this subdivision, the Commission shall require the utility to prove by a preponderance of the evidence that the utility has (i) determined that the utility cannot meet its service obligations, giving due regard, in the Commission's sole discretion, to reliability of service and the need to maintain reliable sources of supply, without an additional fuel resource; (ii) reasonably identified and determined the date and amount of the new fuel resource it needs; (iii) objectively studied available alternative fuel resource options, as verified by the Commission, including options other than a new natural gas capacity contract or contracts to meet the identified and determined need; and (iv) determined that the natural gas capacity contract or contracts are the lowest-cost available option, taking into consideration fixed and variable costs and a reasonable projection of utilization. Absent the Commission's finding that the utility has proven by a preponderance of the evidence that the utility had complied with the requirements of clauses (i), (ii), (iii), and (iv), the Commission shall deny the utility's recovery of such costs. Nothing in this subdivision shall limit the Commission's discretion to review and make a determination as to the reasonableness of the recovery by a utility of costs, including costs incurred under a natural gas capacity contract, that were previously subject to a review under this subdivision.
E. The Commission is authorized to promulgate, in accordance with the provisions of this section, all rules and regulations necessary to allow the recovery by electric utilities of all of their prudently incurred fuel costs under subsections A and C, including the cost of purchased power, as precisely and promptly as possible, with no over-recovery or under-recovery, except as provided in subsection C, in a manner that will tend to assure public confidence and minimize abrupt changes in charges to consumers.
1978, c. 636; 1979, c. 492; 1980, c. 384; 1982, c. 584; 1984, cc. 716, 725; 1989, c. 666; 2004, c. 827; 2006, c. 939; 2007, cc. 888, 933; 2009, c. 244; 2020, c. 661.
§ 56-249.6:1. Financing for certain deferred fuel costs; Phase I Utilities..A. Notwithstanding the provisions of § 56-249.6 or Chapter 3 (§ 56-55 et seq.), an electric utility may petition the Commission for a financing order and the Commission shall either issue (i) such financing order or (ii) an order rejecting the petition, no more than four months from the date of filing such petition and in accordance with the requirements of subdivision 2.
1. The petition shall include (i) an estimate of the total amount of deferred fuel costs that the electric utility has incurred over the time period noted in the petition; (ii) an indication of whether the electric utility proposes to finance all or a portion of the deferred fuel costs using one or more series or tranches of deferred fuel cost bonds; (iii) an estimate and details of the financing costs related to the deferred fuel costs to be financed through the deferred fuel cost bonds; (iv) an estimate of the deferred fuel cost charges necessary to recover the deferred fuel costs and all financing costs and the proposed period for recovery of such costs; (v) a description of any benefits expected to result from the issuance of deferred fuel cost bonds, including the avoidance of or significant mitigation of abrupt and significant increases in rates to the electric utility's customers for the applicable time period; and (vi) direct testimony and exhibits supporting the petition. If the electric utility proposes to finance a portion of the deferred fuel costs, the electric utility shall identify in the petition the specific amount of deferred fuel costs for the applicable time period to be financed using deferred fuel cost bonds. By electing not to finance a portion of the deferred fuel costs for an applicable time period using deferred fuel cost bonds, an electric utility shall not be deemed to waive its right to recover such costs pursuant to a separate proceeding with the Commission.
2. a. If an electric utility petitions the Commission for a financing order pursuant to this section, following notice and an opportunity for hearing, the Commission shall either issue (i) a financing order or (ii) an order rejecting the petition, not more than four months from the date of filing such petition.
b. A financing order issued by the Commission pursuant to this section shall include:
(1) The amount of deferred fuel costs to be financed using deferred fuel cost bonds. The Commission shall describe and estimate the amount of financing costs that may be recovered through deferred fuel cost charges. The financing order shall also specify the period over which deferred fuel costs and financing costs may be recovered and whether the deferred fuel cost bonds may be offered and issued in one or more series or tranches during a fixed period not to exceed one year after the date of the financing order;
(2) A finding that the proposed issuance of deferred fuel cost bonds is in the public interest and the associated deferred fuel cost charges are just and reasonable;
(3) A finding that the structuring and pricing of the deferred fuel cost bonds are reasonably expected to result in reasonable deferred fuel cost charges consistent with market conditions at the time the deferred fuel cost bonds are priced and the terms set forth in such financing order;
(4) A requirement that, for so long as the deferred fuel cost bonds are outstanding and until all financing costs have been paid in full, the imposition and collection of deferred fuel cost charges authorized under a financing order shall be non-bypassable and paid by all retail customers of the electric utility, irrespective of the generation supplier of such customer, except for an exempt retail access customer;
(5) A formula-based true-up mechanism for making annual adjustments to the deferred fuel cost charges that customers are required to pay pursuant to the financing order and for making any adjustments that are necessary to correct for any overcollection or undercollection of the charges or to otherwise ensure the timely payment of deferred fuel cost bonds and financing costs and other required amounts and charges payable in connection with the deferred fuel cost bonds;
(6) The deferred fuel cost property that is, or shall be, created in favor of an electric utility or its successors or assignees and that shall be used to pay or secure deferred fuel cost bonds and all financing costs;
(7) The authority of the electric utility to establish the terms and conditions of the deferred fuel cost bonds, including repayment schedules, expected interest rates, the issuance in one or more series or tranches with different maturity dates, and other financing costs;
(8) A finding that the deferred fuel cost charges shall be allocated among customer classes in accordance with the methodology approved in the electric utility's last fuel factor proceeding;
(9) A requirement that after the final terms of an issuance of deferred fuel cost bonds have been established and before the issuance of deferred fuel cost bonds, the electric utility determines the resulting initial deferred fuel cost charge in accordance with the financing order and that such initial deferred fuel cost charge be final and effective upon the issuance of such deferred fuel cost bonds without further Commission action so long as such initial deferred fuel cost charge is consistent with the financing order;
(10) A method of tracing funds collected as deferred fuel cost charges, or other proceeds of deferred fuel cost property, and a requirement that such method be the method of tracing such funds and determining the identifiable cash proceeds of any deferred fuel cost property subject to the financing order under applicable law; and
(11) Any other conditions not otherwise inconsistent with this section that the Commission determines are appropriate.
c. A financing order issued to an electric utility may provide that creation of the electric utility's deferred fuel cost property is conditioned upon, and simultaneous with, the sale or other transfer for the deferred fuel cost property to an assignee and the pledge of the deferred fuel cost property to secure deferred fuel cost bonds.
d. If the Commission issues a financing order, the Commission shall establish a protocol for the electric utility to annually file a petition or, in the Commission's discretion, a letter setting out application of the formula-based mechanism and, based on estimates of consumption for each rate class and other mathematical factors, requesting administrative approval to make applicable adjustments. The review of the filing shall be limited to determining whether there are any mathematical or clerical errors in the application of the formula-based mechanism relating to the appropriate amount of any overcollection or undercollection of deferred fuel cost charges and the amount of an adjustment. The adjustments shall ensure the recovery of revenues sufficient to provide for the payment of principal, interest, acquisition, defeasance, financing costs, or redemption premium and other fees, costs, and charges in respect of deferred fuel cost bonds approved under the financing order. Within 30 days after receiving an electric utility's request pursuant to this subdivision d, the Commission shall either approve the request or inform the electric utility of mathematical or clerical errors in its calculation. If the Commission informs the electric utility of mathematical or clerical errors in its calculation, the electric utility may correct its error and refile its request. The time frames previously described in this subdivision d shall apply to a refiled request.
e. Subsequent to the transfer of deferred fuel cost property to an assignee or the issuance of deferred fuel cost bonds authorized thereby, whichever is earlier, a financing order shall be irrevocable and, except for changes made pursuant to the formula-based mechanism authorized in this section, the Commission shall not amend, modify, or terminate the financing order by any subsequent action or reduce, impair, postpone, terminate, or otherwise adjust deferred fuel cost charges approved in the financing order. After the issuance of a financing order, the electric utility shall retain sole discretion regarding whether to assign, sell, or otherwise transfer deferred fuel cost property or to cause deferred fuel cost bonds to be issued, including the right to defer or postpone such assignment, sale, transfer, or issuance.
3. At the request of an electric utility, the Commission may commence a proceeding and issue a subsequent financing order that provides for refinancing, retiring, or refunding deferred fuel cost bonds issued pursuant to the original financing order if the Commission finds that the subsequent financing order satisfies all of the criteria specified in this section for a financing order. Effective upon retirement of the refunded deferred fuel cost bonds and the issuance of new deferred fuel cost bonds, the Commission shall adjust the related deferred fuel cost charges accordingly.
4. a. A financing order shall remain in effect and deferred fuel cost property under the financing order shall continue to exist until deferred fuel cost bonds issued pursuant to the financing order have been paid in full or defeased and, in each case, all Commission-approved financing costs of such deferred fuel cost bonds have been recovered in full.
b. A financing order issued to an electric utility shall remain in effect and unabated notwithstanding the reorganization, bankruptcy or other insolvency proceedings, merger, or sale of the electric utility or its successors or assignees.
B. 1. The Commission shall not, in exercising its powers and carrying out its duties regarding any matter within its authority pursuant to this chapter, and notwithstanding any other provision of law, consider the deferred fuel cost bonds issued pursuant to a financing order to be the debt of the electric utility other than for federal income tax purposes, consider the deferred fuel cost charges paid under the financing order to be the revenue of the electric utility for any purpose, or consider the deferred fuel costs or financing costs specified in the financing order to be the costs of the electric utility, nor shall the Commission determine any action taken by an electric utility that is consistent with the financing order to be unjust or unreasonable.
2. The Commission shall not order or otherwise directly or indirectly require an electric utility to use deferred fuel cost bonds to finance any project, addition, plant, facility, extension, capital improvement, equipment, or any other expenditure. After the issuance of a financing order, the electric utility shall retain sole discretion regarding whether to cause the deferred fuel cost bonds to be issued, including the right to defer or postpone such sale, assignment, transfer, or issuance. Nothing shall prevent the electric utility from abandoning the issuance of deferred fuel cost bonds under the financing order by filing with the Commission a statement of abandonment and the reasons therefor. The Commission shall not deny an electric utility its right to recover deferred fuel costs as otherwise provided in this section, or refuse or condition authorization or approval of the issuance and sale by an electric utility of securities or the assumption by the electric utility of liabilities or obligations, solely because of the potential availability of deferred fuel cost bond financing.
C. The electric bills of an electric utility that has obtained a financing order and caused deferred fuel cost bonds to be issued shall comply with the provisions of this subsection; however, the failure of an electric utility to comply with this subsection does not invalidate, impair, or affect any financing order, deferred fuel cost property, deferred fuel cost charge, or deferred fuel cost bonds. The electric utility shall:
1. Explicitly reflect that a portion of the charges on any electric bill represents deferred fuel cost charges approved in a financing order issued to the electric utility and, if the deferred fuel cost property has been transferred to an assignee, such bill shall include a statement to the effect that the assignee is the owner of the rights to deferred fuel cost charges and that the electric utility or another entity, if applicable, is acting as a collection agent or servicer for the assignee. The tariff applicable to customers must indicate the deferred fuel cost charge and the ownership of the charge; and
2. Include the deferred fuel cost charge on each customer's bill as a separate line item and include both the rate and the amount of the charge on each bill.
D. 1. The following provisions shall be applicable to deferred fuel cost property:
a. All deferred fuel cost property that is specified in a financing order shall constitute an existing, present intangible property right or interest therein, notwithstanding that the imposition and collection of deferred fuel cost charges depends on the electric utility, to which the financing order is issued, performing its servicing functions relating to the collection of deferred fuel cost charges and on future electricity consumption. The deferred fuel cost property shall exist (i) regardless of whether or not the revenues or proceeds arising from the deferred fuel cost property have been billed, have accrued, or have been collected and (ii) notwithstanding the fact that the value or amount of the deferred fuel cost property is dependent on the future provision of service to customers by the electric utility or its successors or assignees and the future consumption of electricity by customers;
b. Deferred fuel cost property specified in a financing order shall exist until deferred fuel cost bonds issued pursuant to the financing order are paid in full and all financing costs and other costs of such deferred fuel cost bonds have been recovered in full;
c. All or any portion of deferred fuel cost property specified in a financing order issued to an electric utility may be transferred, sold, conveyed, or assigned to a successor or assignee that is wholly owned, directly or indirectly, by the electric utility and created for the limited purpose of acquiring, owning, or administering deferred fuel cost property or issuing deferred fuel cost bonds under the financing order. All or any portion of deferred fuel cost property may be pledged to secure deferred fuel cost bonds issued pursuant to the financing order, amounts payable to financing parties and to counterparties under any ancillary agreements, and other financing costs. Any transfer, sale, conveyance, assignment, grant of a security interest in or pledge of deferred fuel cost property by an electric utility, or an affiliate of the electric utility, to an assignee, to the extent previously authorized in a financing order, shall not require the prior consent and approval of the Commission;
d. If an electric utility defaults on any required payment of charges arising from deferred fuel cost property specified in a financing order, a court, upon application by an interested party, and without limiting any other remedies available to the applying party, shall order the sequestration and payment of the revenues arising from the deferred fuel cost property to the financing parties or their assignees. Any such financing order shall remain in full force and effect notwithstanding any reorganization, bankruptcy, or other insolvency proceedings with respect to the electric utility or its successors or assignees;
e. The interest of a transferee, purchaser, acquirer, assignee, or pledgee in deferred fuel cost property specified in a financing order issued to an electric utility, and in the revenue and collections arising from that property, shall not be subject to setoff, counterclaim, surcharge, or defense by the electric utility or any other person or in connection with the reorganization, bankruptcy, or other insolvency of the electric utility or any other entity;
f. Any successor to an electric utility, whether pursuant to any reorganization, bankruptcy, or other insolvency proceeding or whether pursuant to any merger or acquisition, sale, or other business combination, or transfer by operation of law, as a result of electric utility restructuring or otherwise, shall perform and satisfy all obligations of, and have the same rights under a financing order as, the electric utility under the financing order in the same manner and to the same extent as the electric utility, including collecting and paying to the person entitled to receive the revenues, collections, payments, or proceeds of the deferred fuel cost property. Nothing in this subdivision f is intended to limit or impair any authority of the Commission concerning the transfer or succession of interests of public utilities; and
g. Deferred fuel cost bonds shall be nonrecourse to the credit or any assets of the electric utility other than the deferred fuel cost property as specified in the financing order and any rights under any ancillary agreement.
2. The following provisions shall be applicable to security interests:
a. The creation, perfection, and enforcement of any security interest in deferred fuel cost property to secure the repayment of the principal and interest and other amounts payable in respect of deferred fuel cost bonds; amounts payable under any indenture, ancillary agreement, or other financing documents in respect of the deferred fuel costs; and other financing costs shall be governed by this subsection and not by the provisions of the Uniform Commercial Code (Titles 8.1A through 8.9A);
b. A security interest in deferred fuel cost property shall be created and enforceable when all of the following have occurred: (i) a financing order is issued, (ii) value is received by the debtor or seller for such deferred fuel cost property, (iii) the debtor or seller has rights in such deferred fuel cost property or the power to transfer rights in such deferred fuel cost property, and (iv) a security agreement granting such security interest is executed and delivered by the debtor or seller. The description of deferred fuel cost property in a security agreement shall be sufficient if the description refers to this section and the financing order creating the deferred fuel cost property;
c. A security interest shall attach without any physical delivery of collateral or other act and, upon the filing of a financing statement with the Commission, the lien of the security interest shall be valid, binding, and perfected against all parties having claims of any kind in tort, contract, or otherwise against the person granting the security interest, regardless of whether the parties have notice of the lien. Also upon this filing, a transfer of an interest in the deferred fuel cost property shall be perfected against all parties having claims of any kind, including any judicial lien or other lien creditors or any claims of the transferor or creditors of the transferor, and shall have priority over all competing claims other than any prior security interest, ownership interest, or assignment in the property previously perfected in accordance with this section;
d. The Commission shall maintain any financing statement filed to perfect any security interest under this section in the same manner that the Commission maintains financing statements filed by transmitting utilities under the Uniform Commercial Code (Titles 8.1A through 8.9A). The filing of a financing statement under this section shall be governed by the provisions regarding the filing of financing statements in the Uniform Commercial Code (Titles 8.1A through 8.9A);
e. The priority of a security interest in deferred fuel cost property shall not be affected by the commingling of deferred fuel cost charges with other amounts. Any pledgee or secured party shall have a perfected security interest in the amount of all deferred fuel cost charges that are deposited in any cash or deposit account of the qualifying utility in which deferred fuel cost charges have been commingled with other funds and any other security interest that may apply to those funds shall be terminated when they are transferred to a segregated account for the assignee or a financing party;
f. No application of the formula-based adjustment mechanism as provided in this section shall affect the validity, perfection, or priority of a security interest in or transfer of deferred fuel cost property; and
g. If a default or termination occurs under the deferred fuel cost bonds, the financing parties or their representatives may foreclose on or otherwise enforce their lien and security interest in any deferred fuel cost property as if they were secured parties with a perfected and prior lien under the Uniform Commercial Code (Titles 8.1A through 8.9A), and the Commission may order that amounts arising from deferred fuel cost charges be transferred to a separate account for the financing parties' benefit, to which their lien and security interest shall apply. On application by or on behalf of the financing parties, the Commission shall order the sequestration and payment to them of revenues arising from the deferred fuel cost charges.
3. a. Any sale, assignment, or other transfer of deferred fuel cost property shall be an absolute transfer and true sale of and not a pledge of, or secured transaction relating to, the transferor's right, title, and interest in, to, and under the deferred fuel cost property if the documents governing the transaction expressly state that the transaction is a sale or other absolute transfer other than for federal and state income tax purposes. For all purposes other than federal and state income tax purposes, the parties' characterization of a transaction as a sale of an interest in deferred fuel cost property shall be conclusive that the transaction is a true sale and that ownership has passed to the party characterized as the purchaser, regardless of any fact or circumstance that might support characterization of the transfer as a secured transaction. A transfer of an interest in deferred fuel cost property shall occur only when all of the following have occurred: (i) the financing order creating the deferred fuel cost property has become effective, (ii) the documents evidencing the transfer of deferred fuel cost property have been executed by the transferor and delivered to the assignee, and (iii) value is received by the transferor for the deferred fuel cost property. After such a transaction, the deferred fuel cost property shall not be subject to any claims of the transferor or the transferor's creditors, other than creditors holding a prior security interest in the deferred fuel cost property perfected in accordance with subdivision 2.
b. The characterization of the sale, assignment, or other transfer as an absolute transfer and true sale, and the corresponding characterization of the interest of the assignee as an ownership interest, shall not be affected or impaired by the occurrence of any of the following factors:
(1) Commingling of deferred fuel cost charges with other amounts;
(2) The retention by the seller of (i) a partial or residual interest, including an equity interest, in the deferred fuel cost property, whether direct or indirect, or whether subordinate or otherwise, or (ii) the right to recover costs associated with taxes, franchise fees, or license fees imposed on the collection of deferred fuel cost charges;
(3) Any recourse that the assignee may have against the seller;
(4) Any right or obligation that the seller may have to repurchase the deferred fuel cost charges;
(5) Any indemnification obligations of the seller;
(6) The obligation of the seller to collect deferred fuel cost charges on behalf of the assignee;
(7) The transferor acting as the servicer of the deferred fuel cost charges or the existence of any contract that authorizes or requires the electric utility, to the extent that any interest in deferred fuel cost property is sold or assigned, to agree with the assignee or any financing party that it will continue to operate its system to provide service to its customers, will collect amounts in respect of the deferred fuel cost charges for the benefit and account of such assignee or financing party, and will account for and remit such amounts to or for the account of such assignee or financing party;
(8) The treatment of the sale, conveyance, assignment, or other transfer for tax, financial reporting, or other purposes;
(9) The granting or providing to bondholders of a preferred right to the deferred fuel cost property or credit enhancement by the electric utility or its affiliates with respect to the deferred fuel cost bonds; or
(10) Any application of the formula-based adjustment mechanism as provided in this section.
c. Any right that an electric utility has in the deferred fuel cost property before its pledge, sale, or transfer or any other right created under this section or created in the financing order and assignable under this section or assignable pursuant to a financing order shall be property in the form of a contract right or a chose in action. Transfer of an interest in deferred fuel cost property to an assignee shall be enforceable only when all of the following have occurred: (i) a financing order is issued, (ii) value is received by the transferor for such deferred fuel cost property, (iii) the transferor has rights in such deferred fuel cost property or the power to transfer rights in such deferred fuel cost property, and (iv) transfer documents in connection with the issuance of deferred fuel cost bonds are executed and delivered by the transferor. An enforceable transfer of an interest in deferred fuel cost property to an assignee shall be perfected against all third parties, including subsequent judicial or other lien creditors, when a notice of that transfer has been given by the filing of a financing statement in accordance with subdivision 2 c. The transfer shall be perfected against third parties as of the date of filing.
d. The Commission shall maintain any financing statement filed to perfect any sale, assignment, or transfer of deferred fuel cost property under this section in the same manner that the Commission maintains financing statements filed by transmitting utilities under the Uniform Commercial Code (Titles 8.1A through 8.9A). The filing of any financing statement under this section shall be governed by the provisions regarding the filing of financing statements in the Uniform Commercial Code (Titles 8.1A through 8.9A). The filing of such a financing statement shall be the only method of perfecting a transfer of deferred fuel cost property.
e. The priority of a transfer perfected under this section shall not be impaired by any later modification of the financing order or deferred fuel cost property or by the commingling of funds arising from deferred fuel cost property with other funds. Any other security interest that may apply to those funds, other than a security interest perfected under subdivision 2, shall be terminated when they are transferred to a segregated account for the assignee or a financing party. If deferred fuel cost property has been transferred to an assignee or financing party, any proceeds of that property shall be held in trust for the assignee or financing party.
f. The priority of the conflicting interests of assignees in the same interest or rights in any deferred fuel cost property shall be determined as follows:
(1) Conflicting perfected interests or rights of assignees shall rank according to priority in time of perfection. Priority shall date from the time a filing covering the transfer is made in accordance with subdivision 2 c;
(2) A perfected interest or right of an assignee shall have priority over a conflicting unperfected interest or right of an assignee; and
(3) A perfected interest or right of an assignee shall have priority over a person who becomes a lien creditor after the perfection of such assignee's interest or right.
E. The description of deferred fuel cost property being transferred to an assignee in any sale agreement, purchase agreement, or other transfer agreement, granted or pledged to a pledgee in any security agreement, pledge agreement, or other security document, or indicated in any financing statement, shall only be sufficient if such description or indication refers to the financing order that created the deferred fuel cost property and states that the agreement or financing statement covers all or part of the property described in the financing order. This section shall apply to all purported transfers of, and all purported grants or liens or security interests in, deferred fuel cost property, regardless of whether the related sale agreement, purchase agreement, other transfer agreement, security agreement, pledge agreement, or other security document was entered into, or any financing statement was filed.
F. All financing statements referenced in this section shall be subject to Part 5 of Title 8.9A (§ 8.9A-501 et seq.) of the Uniform Commercial Code, except that the requirement as to continuation statements shall not apply.
G. The laws of the Commonwealth shall govern the validity, enforceability, attachment, perfection, priority, and exercise of remedies with respect to the transfer of an interest or right or the pledge or creation of a security interest in any deferred fuel cost property.
H. Neither the Commonwealth nor its political subdivisions shall be liable on any deferred fuel cost bonds, and the bonds shall not be a debt or a general obligation of the Commonwealth or any of its political subdivisions, agencies, or instrumentalities, nor shall they be special obligations or indebtedness of the Commonwealth or any of its agencies or political subdivisions. An issue of deferred fuel cost bonds shall not, directly, indirectly, or contingently, obligate the Commonwealth or any agency, political subdivision, or instrumentality of the Commonwealth to levy any tax or make any appropriation for payment of the deferred fuel cost bonds, other than in their capacity as consumers of electricity. All deferred fuel cost bonds shall contain on the face thereof a statement to the following effect: "NEITHER THE FULL FAITH AND CREDIT NOR THE TAXING POWER OF THE COMMONWEALTH IS PLEDGED TO THE PAYMENT OF THE PRINCIPAL OF, OR INTEREST ON, THIS BOND."
I. All of the following entities may legally invest any sinking funds, moneys, or other funds in deferred fuel cost bonds:
1. Subject to applicable statutory restrictions on state or local investment authority, the Commonwealth, units of local government, political subdivisions, public bodies, and public officers, except for members of the Commission;
2. Banks and bankers, savings and loan associations, credit unions, trust companies, savings banks and institutions, investment companies, insurance companies, insurance associations, and other persons carrying on a banking or insurance business;
3. Personal representatives, guardians, trustees, and other fiduciaries; and
4. All other persons authorized to invest in bonds or other obligations of a similar nature.
J. 1. The Commonwealth and its agencies, including the Commission, pledge and agree with bondholders, the owners of the deferred fuel cost property, and other financing parties that the Commonwealth and its agencies shall not take any action listed in this subdivision. This subsection does not preclude limitation or alteration if full compensation is made by law for the full protection of the deferred fuel cost charges collected pursuant to a financing order and of the bondholders and any assignee or financing party entering into a contract with the electric utility. The Commonwealth and its agencies, including the Commission, shall not:
a. Alter the provisions of this section that authorize the Commission to create an irrevocable contract right or chose in action by the issuance of a financing order, to create deferred fuel cost property, and to make the deferred fuel cost charges imposed by a financing order irrevocable, binding, or nonbypassable charges;
b. Take or permit any action that impairs or would impair the value of deferred fuel cost property or the security for the deferred fuel cost bonds or revises the deferred fuel costs for which recovery is authorized;
c. In any way impair the rights and remedies of the bondholders, assignees, and other financing parties; or
d. Except for changes made pursuant to the formula-based adjustment mechanism authorized under this section, reduce, alter, or impair deferred fuel cost charges that are to be imposed, billed, charged, collected, and remitted for the benefit of the bondholders, any assignee, and any other financing parties until any and all principal, interest, premium, financing costs and other fees, expenses, or charges incurred, and any contracts to be performed, in connection with the related deferred fuel cost bonds have been paid and performed in full.
2. Any person that issues deferred fuel cost bonds may include the language specified in subdivision 1 in the deferred fuel cost bonds and related documentation.
K. An assignee or financing party shall not be considered an electric utility or person providing electric service by virtue of engaging in the transactions described in this section.
L. If there is a conflict between this section and any other law regarding the attachment, assignment, or perfection, or the effect of perfection, or priority of, assignment or transfer of, or security interest in deferred fuel cost property, this section shall govern.
M. In making determinations under this section, the Commission may engage an outside consultant and counsel.
N. If any provision of this section is held invalid or is invalidated, superseded, replaced, repealed, or expires for any reason, that occurrence shall not affect the validity of any action allowed under this section that is taken by an electric utility, an assignee, a financing party, a collection agent, or a party to an ancillary agreement, and any such action shall remain in full force and effect with respect to all deferred fuel cost bonds issued or authorized in a financing order issued under this section before the date that such provision is held invalid or is invalidated, superseded, replaced, or repealed, or expires for any reason.
O. As used in this section:
"Ancillary agreement" means a bond, insurance policy, letter of credit, reserve account, surety bond, interest rate lock or swap arrangement, hedging arrangement, liquidity or credit support arrangement, or other financial arrangement entered into in connection with deferred fuel cost bonds.
"Assignee" means a legally recognized entity to which an electric utility assigns, sells, or transfers, other than as a security, all or a portion of its interest in or right to deferred fuel cost property. "Assignee" includes a corporation, limited liability company, general partnership or limited partnership, public authority trust, financing entity, or other entity to which an assignee assigns, sells, or transfers, other than as a security, all or a portion of its interest in or right to deferred fuel cost property.
"Bondholder" means a person who holds a deferred fuel cost bond.
"Deferred fuel cost bonds" means bonds debentures, notes, certificates of participation, certificates of beneficial interest, certificates of ownership, or other evidences of indebtedness or ownership that are issued in one or more series or tranches by an electric utility or its assignee pursuant to a financing order, the proceeds of which are used directly or indirectly to recover, finance, or refinance Commission-approved deferred fuel costs and financing costs, and that are secured by or payable from deferred fuel cost property. If certificates of participation or ownership are issued, references in this section to principal, interest, or premium shall be construed to refer to comparable amounts under those certificates.
"Deferred fuel cost charge" means the nonbypassable charges authorized by the Commission to repay, finance, or refinance deferred fuel costs and financing costs (i) imposed on and part of all retail customer bills, except those of exempt retail access customers; (ii) collected by an electric utility or its successor or assignees, or a collection agent, in full, separate and apart from the electric utility's base rates; and (iii) paid by all retail customers of the electric utility, irrespective of the generation supplier of such customer, except for an exempt retail access customer.
"Deferred fuel cost property" includes:
1. All rights and interests of an electric utility or successor or assignee of the electric utility under a financing order, including the right to impose, bill, charge, collect, and receive deferred fuel cost charges authorized under the financing order and to obtain periodic adjustments to such charges as provided in the financing order; and
2. All revenues, collections, claims, rights to payments, payments, money, or proceeds arising from the rights and interests specified in the financing order, regardless of whether such revenues, collections, claims, rights to payment, payments, money, or proceeds are imposed, billed, received, collected, or maintained together with or commingled with other revenues, collections, rights to payment, payments, money, or proceeds.
"Deferred fuel costs" means the unrecovered amounts of previously incurred costs of fuel used to generate electricity, including the costs of purchased power, that have been deferred by an electric utility for future recovery from the utility's customers, along with financing costs on the utility's fuel deferral balance.
"Electric utility" means a Phase I Utility.
"Exempt retail access customer" means a retail customer of an electric utility that, pursuant to the provisions of § 56-577 or 56-577.1, purchased electric energy exclusively from a supplier of electric energy licensed to sell retail electric energy exclusively within the Commonwealth other than the electric utility, or that purchased electric energy from the electric utility pursuant to a Commission-approved market-based tariff, during the period when the deferred fuel costs to be financed were incurred. Such exemption shall be prorated to the extent an otherwise exempt retail customer purchased electric energy from the electric utility, in which case the retail customer shall be responsible for its pro rata share of deferred fuel cost charges authorized under a financing order.
"Financing costs" means:
1. Interest and any premium, including any acquisition, defeasance, or redemption premium, payable on deferred fuel cost bonds;
2. Any payment required under any indenture, ancillary agreement, or other financing documents pertaining to deferred fuel cost bonds and any amount required to fund or replenish a reserve account or other accounts established under the terms of any indenture, ancillary agreement, or other financing documents pertaining to deferred fuel cost bonds;
3. Any other costs related to structuring, offering, issuing, supporting, repaying, refunding, servicing, and complying with deferred fuel cost bonds, including service fees, accounting and auditing fees, trustee fees, legal fees, consulting fees, structuring adviser fees, administrative fees, placement and underwriting fees, independent director and manager fees, capitalized interest, rating agency fees, stock exchange listing and compliance fees, security registration fees, filing fees, information technology programming costs, and any other costs necessary to otherwise ensure the timely payment of deferred fuel cost bonds or other amounts or charges payable in connection with the bonds, including costs related to obtaining the financing order;
4. Any taxes and license fees or other fees imposed on the revenues generated from the collection of deferred fuel cost charges or otherwise resulting from the collection of deferred fuel cost charges, in any such case whether paid, payable, or accrued;
5. Any state and local taxes, franchise, gross receipts, and other taxes or similar charges, including regulatory assessment fees, whether paid, payable, or accrued;
6. Any costs incurred by the Commission for any outside consultants or counsel retained in connection with the securitization of deferred fuel costs; and
7. Any financing costs on the utility's fuel deferral balance prior to issuance of any fuel cost bonds, calculated at the utility's approved weighted average cost of capital.
"Financing order" means an order that authorizes the issuance of deferred fuel cost bonds; the imposition, collection, and periodic adjustments of a deferred fuel cost charge; the creation of deferred fuel cost property; the sale, assignment, or transfer of deferred fuel cost property to an assignee; and any other actions necessary or advisable to take actions described in the financing order.
"Financing party" means bondholders and trustees, collateral agents, any party under an ancillary agreement, or any other person acting for the benefit of bondholders.
"Financing statement" has the same meaning as provided in § 8.9A-102 of the Uniform Commercial Code.
"Phase I Utility" has the same meaning as provided in subdivision A 1 of § 56-585.1.
"Pledgee" means a financing party to which an electric utility or its successors or assignees mortgages, negotiates, pledges, or creates a security interest or lien on all or any portion of its interest in or right to deferred fuel cost property.
§ 56-249.6:2. Financing for certain deferred fuel costs; Phase II Utilities.A. Notwithstanding the provisions of § 56-249.6 or Chapter 3 (§ 56-55 et seq.), an electric utility, on or before July 1, 2024, may petition the Commission for a financing order and the Commission shall either issue (i) such financing order or (ii) an order rejecting the petition, no more than four months from the date of filing such petition and in accordance with the requirements of subdivision 2.
1. The petition shall include (i) an estimate of the total amount of deferred fuel costs that the electric utility has incurred over the time period noted in the petition; (ii) an indication of whether the electric utility proposes to finance all or a portion of the deferred fuel costs using one or more series or tranches of deferred fuel cost bonds; (iii) an estimate and details of the financing costs related to the deferred fuel costs to be financed through the deferred fuel cost bonds; (iv) an estimate of the deferred fuel cost charges necessary to recover the deferred fuel costs and all financing costs and the proposed period for recovery of such costs; (v) a description of any benefits expected to result from the issuance of deferred fuel cost bonds, including the avoidance of or significant mitigation of abrupt and significant increases in rates to the electric utility's customers for the applicable time period; and (vi) direct testimony and exhibits supporting the petition. If the electric utility proposes to finance a portion of the deferred fuel costs, the electric utility shall identify in the petition the specific amount of deferred fuel costs for the applicable time period to be financed using deferred fuel cost bonds. By electing not to finance a portion of the deferred fuel costs for an applicable time period using deferred fuel cost bonds, an electric utility shall not be deemed to waive its right to recover such costs pursuant to a separate proceeding with the Commission.
2. a. If an electric utility petitions the Commission for a financing order pursuant to this section, following notice and an opportunity for hearing, the Commission shall either issue (i) a financing order or (ii) an order rejecting the petition, not more than four months from the date of filing such petition.
b. A financing order issued by the Commission pursuant to this section shall include:
(1) The amount of deferred fuel costs to be financed using deferred fuel cost bonds. The Commission shall describe and estimate the amount of financing costs that may be recovered through deferred fuel cost charges. The financing order shall also specify the period over which deferred fuel costs and financing costs may be recovered and whether the deferred fuel cost bonds may be offered and issued in one or more series or tranches during a fixed period not to exceed one year after the date of the financing order;
(2) A finding that the proposed issuance of deferred fuel cost bonds is in the public interest and the associated deferred fuel cost charges are just and reasonable;
(3) A finding that the structuring and pricing of the deferred fuel cost bonds are reasonably expected to result in reasonable deferred fuel cost charges consistent with market conditions at the time the deferred fuel cost bonds are priced and the terms set forth in such financing order;
(4) A requirement that, for so long as the deferred fuel cost bonds are outstanding and until all financing costs have been paid in full, the imposition and collection of deferred fuel cost charges authorized under a financing order shall be non-bypassable and paid by all retail customers of the electric utility, irrespective of the generation supplier of such customer, except for an exempt retail access customer;
(5) A formula-based true-up mechanism for making annual adjustments to the deferred fuel cost charges that customers are required to pay pursuant to the financing order and for making any adjustments that are necessary to correct for any overcollection or undercollection of the charges or to otherwise ensure the timely payment of deferred fuel cost bonds and financing costs and other required amounts and charges payable in connection with the deferred fuel cost bonds;
(6) The deferred fuel cost property that is, or shall be, created in favor of an electric utility or its successors or assignees and that shall be used to pay or secure deferred fuel cost bonds and all financing costs;
(7) The authority of the electric utility to establish the terms and conditions of the deferred fuel cost bonds, including repayment schedules, expected interest rates, the issuance in one or more series or tranches with different maturity dates, and other financing costs;
(8) A finding that the deferred fuel cost charges shall be allocated among customer classes in accordance with the methodology approved in the electric utility's last fuel factor proceeding;
(9) A requirement that after the final terms of an issuance of deferred fuel cost bonds have been established and before the issuance of deferred fuel cost bonds, the electric utility determines the resulting initial deferred fuel cost charge in accordance with the financing order and that such initial deferred fuel cost charge be final and effective upon the issuance of such deferred fuel cost bonds without further Commission action so long as such initial deferred fuel cost charge is consistent with the financing order;
(10) A method of tracing funds collected as deferred fuel cost charges, or other proceeds of deferred fuel cost property, and a requirement that such method be the method of tracing such funds and determining the identifiable cash proceeds of any deferred fuel cost property subject to the financing order under applicable law; and
(11) Any other conditions not otherwise inconsistent with this section that the Commission determines are appropriate.
c. A financing order issued to an electric utility may provide that creation of the electric utility's deferred fuel cost property is conditioned upon, and simultaneous with, the sale or other transfer for the deferred fuel cost property to an assignee and the pledge of the deferred fuel cost property to secure deferred fuel cost bonds.
d. If the Commission issues a financing order, the Commission shall establish a protocol for the electric utility to annually file a petition or, in the Commission's discretion, a letter setting out application of the formula-based mechanism and, based on estimates of consumption for each rate class and other mathematical factors, requesting administrative approval to make applicable adjustments. The review of the filing shall be limited to determining whether there are any mathematical or clerical errors in the application of the formula-based mechanism relating to the appropriate amount of any overcollection or undercollection of deferred fuel cost charges and the amount of an adjustment. The adjustments shall ensure the recovery of revenues sufficient to provide for the payment of principal, interest, acquisition, defeasance, financing costs, or redemption premium and other fees, costs, and charges in respect of deferred fuel cost bonds approved under the financing order. Within 30 days after receiving an electric utility's request pursuant to this subdivision d, the Commission shall either approve the request or inform the electric utility of mathematical or clerical errors in its calculation. If the Commission informs the electric utility of mathematical or clerical errors in its calculation, the electric utility may correct its error and refile its request. The time frames previously described in this subdivision d shall apply to a refiled request.
e. Subsequent to the transfer of deferred fuel cost property to an assignee or the issuance of deferred fuel cost bonds authorized thereby, whichever is earlier, a financing order shall be irrevocable and, except for changes made pursuant to the formula-based mechanism authorized in this section, the Commission shall not amend, modify, or terminate the financing order by any subsequent action or reduce, impair, postpone, terminate, or otherwise adjust deferred fuel cost charges approved in the financing order. After the issuance of a financing order, the electric utility shall retain sole discretion regarding whether to assign, sell, or otherwise transfer deferred fuel cost property or to cause deferred fuel cost bonds to be issued, including the right to defer or postpone such assignment, sale, transfer, or issuance.
3. At the request of an electric utility, the Commission may commence a proceeding and issue a subsequent financing order that provides for refinancing, retiring, or refunding deferred fuel cost bonds issued pursuant to the original financing order if the Commission finds that the subsequent financing order satisfies all of the criteria specified in this section for a financing order. Effective upon retirement of the refunded deferred fuel cost bonds and the issuance of new deferred fuel cost bonds, the Commission shall adjust the related deferred fuel cost charges accordingly.
4. a. A financing order shall remain in effect and deferred fuel cost property under the financing order shall continue to exist until deferred fuel cost bonds issued pursuant to the financing order have been paid in full or defeased and, in each case, all Commission-approved financing costs of such deferred fuel cost bonds have been recovered in full.
b. A financing order issued to an electric utility shall remain in effect and unabated notwithstanding the reorganization, bankruptcy or other insolvency proceedings, merger, or sale of the electric utility or its successors or assignees.
B. 1. The Commission shall not, in exercising its powers and carrying out its duties regarding any matter within its authority pursuant to this chapter, and notwithstanding any other provision of law, consider the deferred fuel cost bonds issued pursuant to a financing order to be the debt of the electric utility other than for federal income tax purposes, consider the deferred fuel cost charges paid under the financing order to be the revenue of the electric utility for any purpose, or consider the deferred fuel costs or financing costs specified in the financing order to be the costs of the electric utility, nor shall the Commission determine any action taken by an electric utility that is consistent with the financing order to be unjust or unreasonable.
2. The Commission shall not order or otherwise directly or indirectly require an electric utility to use deferred fuel cost bonds to finance any project, addition, plant, facility, extension, capital improvement, equipment, or any other expenditure. After the issuance of a financing order, the electric utility shall retain sole discretion regarding whether to cause the deferred fuel cost bonds to be issued, including the right to defer or postpone such sale, assignment, transfer, or issuance. Nothing shall prevent the electric utility from abandoning the issuance of deferred fuel cost bonds under the financing order by filing with the Commission a statement of abandonment and the reasons therefor. The Commission shall not deny an electric utility its right to recover deferred fuel costs as otherwise provided in this section, or refuse or condition authorization or approval of the issuance and sale by an electric utility of securities or the assumption by the electric utility of liabilities or obligations, solely because of the potential availability of deferred fuel cost bond financing.
C. The electric bills of an electric utility that has obtained a financing order and caused deferred fuel cost bonds to be issued shall comply with the provisions of this subsection; however, the failure of an electric utility to comply with this subsection does not invalidate, impair, or affect any financing order, deferred fuel cost property, deferred fuel cost charge, or deferred fuel cost bonds. The electric utility shall:
1. Explicitly reflect that a portion of the charges on any electric bill represents deferred fuel cost charges approved in a financing order issued to the electric utility and, if the deferred fuel cost property has been transferred to an assignee, such bill shall include a statement to the effect that the assignee is the owner of the rights to deferred fuel cost charges and that the electric utility or another entity, if applicable, is acting as a collection agent or servicer for the assignee. The tariff applicable to customers must indicate the deferred fuel cost charge and the ownership of the charge; and
2. Include the deferred fuel cost charge on each customer's bill as a separate line item and include both the rate and the amount of the charge on each bill.
D. 1. The following provisions shall be applicable to deferred fuel cost property:
a. All deferred fuel cost property that is specified in a financing order shall constitute an existing, present intangible property right or interest therein, notwithstanding that the imposition and collection of deferred fuel cost charges depends on the electric utility, to which the financing order is issued, performing its servicing functions relating to the collection of deferred fuel cost charges and on future electricity consumption. The deferred fuel cost property shall exist (i) regardless of whether or not the revenues or proceeds arising from the deferred fuel cost property have been billed, have accrued, or have been collected and (ii) notwithstanding the fact that the value or amount of the deferred fuel cost property is dependent on the future provision of service to customers by the electric utility or its successors or assignees and the future consumption of electricity by customers;
b. Deferred fuel cost property specified in a financing order shall exist until deferred fuel cost bonds issued pursuant to the financing order are paid in full and all financing costs and other costs of such deferred fuel cost bonds have been recovered in full;
c. All or any portion of deferred fuel cost property specified in a financing order issued to an electric utility may be transferred, sold, conveyed, or assigned to a successor or assignee that is wholly owned, directly or indirectly, by the electric utility and created for the limited purpose of acquiring, owning, or administering deferred fuel cost property or issuing deferred fuel cost bonds under the financing order. All or any portion of deferred fuel cost property may be pledged to secure deferred fuel cost bonds issued pursuant to the financing order, amounts payable to financing parties and to counterparties under any ancillary agreements, and other financing costs. Any transfer, sale, conveyance, assignment, grant of a security interest in or pledge of deferred fuel cost property by an electric utility, or an affiliate of the electric utility, to an assignee, to the extent previously authorized in a financing order, shall not require the prior consent and approval of the Commission;
d. If an electric utility defaults on any required payment of charges arising from deferred fuel cost property specified in a financing order, a court, upon application by an interested party, and without limiting any other remedies available to the applying party, shall order the sequestration and payment of the revenues arising from the deferred fuel cost property to the financing parties or their assignees. Any such financing order shall remain in full force and effect notwithstanding any reorganization, bankruptcy, or other insolvency proceedings with respect to the electric utility or its successors or assignees;
e. The interest of a transferee, purchaser, acquirer, assignee, or pledgee in deferred fuel cost property specified in a financing order issued to an electric utility, and in the revenue and collections arising from that property, shall not be subject to setoff, counterclaim, surcharge, or defense by the electric utility or any other person or in connection with the reorganization, bankruptcy, or other insolvency of the electric utility or any other entity;
f. Any successor to an electric utility, whether pursuant to any reorganization, bankruptcy, or other insolvency proceeding or whether pursuant to any merger or acquisition, sale, or other business combination, or transfer by operation of law, as a result of electric utility restructuring or otherwise, shall perform and satisfy all obligations of, and have the same rights under a financing order as, the electric utility under the financing order in the same manner and to the same extent as the electric utility, including collecting and paying to the person entitled to receive the revenues, collections, payments, or proceeds of the deferred fuel cost property. Nothing in this subdivision f is intended to limit or impair any authority of the Commission concerning the transfer or succession of interests of public utilities; and
g. Deferred fuel cost bonds shall be nonrecourse to the credit or any assets of the electric utility other than the deferred fuel cost property as specified in the financing order and any rights under any ancillary agreement.
2. The following provisions shall be applicable to security interests:
a. The creation, perfection, and enforcement of any security interest in deferred fuel cost property to secure the repayment of the principal and interest and other amounts payable in respect of deferred fuel cost bonds; amounts payable under any indenture, ancillary agreement, or other financing documents in respect of the deferred fuel costs; and other financing costs shall be governed by this subsection and not by the provisions of the Uniform Commercial Code (Titles 8.1A through 8.9A);
b. A security interest in deferred fuel cost property shall be created and enforceable when all of the following have occurred: (i) a financing order is issued, (ii) value is received by the debtor or seller for such deferred fuel cost property, (iii) the debtor or seller has rights in such deferred fuel cost property or the power to transfer rights in such deferred fuel cost property, and (iv) a security agreement granting such security interest is executed and delivered by the debtor or seller. The description of deferred fuel cost property in a security agreement shall be sufficient if the description refers to this section and the financing order creating the deferred fuel cost property;
c. A security interest shall attach without any physical delivery of collateral or other act and, upon the filing of a financing statement with the Commission, the lien of the security interest shall be valid, binding, and perfected against all parties having claims of any kind in tort, contract, or otherwise against the person granting the security interest, regardless of whether the parties have notice of the lien. Also upon this filing, a transfer of an interest in the deferred fuel cost property shall be perfected against all parties having claims of any kind, including any judicial lien or other lien creditors or any claims of the transferor or creditors of the transferor, and shall have priority over all competing claims other than any prior security interest, ownership interest, or assignment in the property previously perfected in accordance with this section;
d. The Commission shall maintain any financing statement filed to perfect any security interest under this section in the same manner that the Commission maintains financing statements filed by transmitting utilities under the Uniform Commercial Code (Titles 8.1A through 8.9A). The filing of a financing statement under this section shall be governed by the provisions regarding the filing of financing statements in the Uniform Commercial Code (Titles 8.1A through 8.9A);
e. The priority of a security interest in deferred fuel cost property shall not be affected by the commingling of deferred fuel cost charges with other amounts. Any pledgee or secured party shall have a perfected security interest in the amount of all deferred fuel cost charges that are deposited in any cash or deposit account of the qualifying utility in which deferred fuel cost charges have been commingled with other funds and any other security interest that may apply to those funds shall be terminated when they are transferred to a segregated account for the assignee or a financing party;
f. No application of the formula-based adjustment mechanism as provided in this section shall affect the validity, perfection, or priority of a security interest in or transfer of deferred fuel cost property; and
g. If a default or termination occurs under the deferred fuel cost bonds, the financing parties or their representatives may foreclose on or otherwise enforce their lien and security interest in any deferred fuel cost property as if they were secured parties with a perfected and prior lien under the Uniform Commercial Code (Titles 8.1A through 8.9A), and the Commission may order that amounts arising from deferred fuel cost charges be transferred to a separate account for the financing parties' benefit, to which their lien and security interest shall apply. On application by or on behalf of the financing parties, the Commission shall order the sequestration and payment to them of revenues arising from the deferred fuel cost charges.
3. a. Any sale, assignment, or other transfer of deferred fuel cost property shall be an absolute transfer and true sale of and not a pledge of, or secured transaction relating to, the transferor's right, title, and interest in, to, and under the deferred fuel cost property if the documents governing the transaction expressly state that the transaction is a sale or other absolute transfer other than for federal and state income tax purposes. For all purposes other than federal and state income tax purposes, the parties' characterization of a transaction as a sale of an interest in deferred fuel cost property shall be conclusive that the transaction is a true sale and that ownership has passed to the party characterized as the purchaser, regardless of any fact or circumstance that might support characterization of the transfer as a secured transaction. A transfer of an interest in deferred fuel cost property shall occur only when all of the following have occurred: (i) the financing order creating the deferred fuel cost property has become effective, (ii) the documents evidencing the transfer of deferred fuel cost property have been executed by the transferor and delivered to the assignee, and (iii) value is received by the transferor for the deferred fuel cost property. After such a transaction, the deferred fuel cost property shall not be subject to any claims of the transferor or the transferor's creditors, other than creditors holding a prior security interest in the deferred fuel cost property perfected in accordance with subdivision 2.
b. The characterization of the sale, assignment, or other transfer as an absolute transfer and true sale, and the corresponding characterization of the interest of the assignee as an ownership interest, shall not be affected or impaired by the occurrence of any of the following factors:
(1) Commingling of deferred fuel cost charges with other amounts;
(2) The retention by the seller of (i) a partial or residual interest, including an equity interest, in the deferred fuel cost property, whether direct or indirect, or whether subordinate or otherwise, or (ii) the right to recover costs associated with taxes, franchise fees, or license fees imposed on the collection of deferred fuel cost charges;
(3) Any recourse that the assignee may have against the seller;
(4) Any right or obligation that the seller may have to repurchase the deferred fuel cost charges;
(5) Any indemnification obligations of the seller;
(6) The obligation of the seller to collect deferred fuel cost charges on behalf of the assignee;
(7) The transferor acting as the servicer of the deferred fuel cost charges or the existence of any contract that authorizes or requires the electric utility, to the extent that any interest in deferred fuel cost property is sold or assigned, to agree with the assignee or any financing party that it will continue to operate its system to provide service to its customers, will collect amounts in respect of the deferred fuel cost charges for the benefit and account of such assignee or financing party, and will account for and remit such amounts to or for the account of such assignee or financing party;
(8) The treatment of the sale, conveyance, assignment, or other transfer for tax, financial reporting, or other purposes;
(9) The granting or providing to bondholders of a preferred right to the deferred fuel cost property or credit enhancement by the electric utility or its affiliates with respect to the deferred fuel cost bonds; or
(10) Any application of the formula-based adjustment mechanism as provided in this section.
c. Any right that an electric utility has in the deferred fuel cost property before its pledge, sale, or transfer or any other right created under this section or created in the financing order and assignable under this section or assignable pursuant to a financing order shall be property in the form of a contract right or a chose in action. Transfer of an interest in deferred fuel cost property to an assignee shall be enforceable only when all of the following have occurred: (i) a financing order is issued, (ii) value is received by the transferor for such deferred fuel cost property, (iii) the transferor has rights in such deferred fuel cost property or the power to transfer rights in such deferred fuel cost property, and (iv) transfer documents in connection with the issuance of deferred fuel cost bonds are executed and delivered by the transferor. An enforceable transfer of an interest in deferred fuel cost property to an assignee shall be perfected against all third parties, including subsequent judicial or other lien creditors, when a notice of that transfer has been given by the filing of a financing statement in accordance with subdivision 2 c. The transfer shall be perfected against third parties as of the date of filing.
d. The Commission shall maintain any financing statement filed to perfect any sale, assignment, or transfer of deferred fuel cost property under this section in the same manner that the Commission maintains financing statements filed by transmitting utilities under the Uniform Commercial Code (Titles 8.1A through 8.9A). The filing of any financing statement under this section shall be governed by the provisions regarding the filing of financing statements in the Uniform Commercial Code (Titles 8.1A through 8.9A). The filing of such a financing statement shall be the only method of perfecting a transfer of deferred fuel cost property.
e. The priority of a transfer perfected under this section shall not be impaired by any later modification of the financing order or deferred fuel cost property or by the commingling of funds arising from deferred fuel cost property with other funds. Any other security interest that may apply to those funds, other than a security interest perfected under subdivision 2, shall be terminated when they are transferred to a segregated account for the assignee or a financing party. If deferred fuel cost property has been transferred to an assignee or financing party, any proceeds of that property shall be held in trust for the assignee or financing party.
f. The priority of the conflicting interests of assignees in the same interest or rights in any deferred fuel cost property shall be determined as follows:
(1) Conflicting perfected interests or rights of assignees shall rank according to priority in time of perfection. Priority shall date from the time a filing covering the transfer is made in accordance with subdivision 2 c;
(2) A perfected interest or right of an assignee shall have priority over a conflicting unperfected interest or right of an assignee; and
(3) A perfected interest or right of an assignee shall have priority over a person who becomes a lien creditor after the perfection of such assignee's interest or right.
E. The description of deferred fuel cost property being transferred to an assignee in any sale agreement, purchase agreement, or other transfer agreement, granted or pledged to a pledgee in any security agreement, pledge agreement, or other security document, or indicated in any financing statement, shall only be sufficient if such description or indication refers to the financing order that created the deferred fuel cost property and states that the agreement or financing statement covers all or part of the property described in the financing order. This section shall apply to all purported transfers of, and all purported grants or liens or security interests in, deferred fuel cost property, regardless of whether the related sale agreement, purchase agreement, other transfer agreement, security agreement, pledge agreement, or other security document was entered into, or any financing statement was filed.
F. All financing statements referenced in this section shall be subject to Part 5 of Title 8.9A (§ 8.9A-501 et seq.) of the Uniform Commercial Code, except that the requirement as to continuation statements shall not apply.
G. The laws of the Commonwealth shall govern the validity, enforceability, attachment, perfection, priority, and exercise of remedies with respect to the transfer of an interest or right or the pledge or creation of a security interest in any deferred fuel cost property.
H. Neither the Commonwealth nor its political subdivisions shall be liable on any deferred fuel cost bonds, and the bonds shall not be a debt or a general obligation of the Commonwealth or any of its political subdivisions, agencies, or instrumentalities, nor shall they be special obligations or indebtedness of the Commonwealth or any of its agencies or political subdivisions. An issue of deferred fuel cost bonds shall not, directly, indirectly, or contingently, obligate the Commonwealth or any agency, political subdivision, or instrumentality of the Commonwealth to levy any tax or make any appropriation for payment of the deferred fuel cost bonds, other than in their capacity as consumers of electricity. All deferred fuel cost bonds shall contain on the face thereof a statement to the following effect: "NEITHER THE FULL FAITH AND CREDIT NOR THE TAXING POWER OF THE COMMONWEALTH IS PLEDGED TO THE PAYMENT OF THE PRINCIPAL OF, OR INTEREST ON, THIS BOND."
I. All of the following entities may legally invest any sinking funds, moneys, or other funds in deferred fuel cost bonds:
1. Subject to applicable statutory restrictions on state or local investment authority, the Commonwealth, units of local government, political subdivisions, public bodies, and public officers, except for members of the Commission;
2. Banks and bankers, savings and loan associations, credit unions, trust companies, savings banks and institutions, investment companies, insurance companies, insurance associations, and other persons carrying on a banking or insurance business;
3. Personal representatives, guardians, trustees, and other fiduciaries; and
4. All other persons authorized to invest in bonds or other obligations of a similar nature.
J. 1. The Commonwealth and its agencies, including the Commission, pledge and agree with bondholders, the owners of the deferred fuel cost property, and other financing parties that the Commonwealth and its agencies shall not take any action listed in this subdivision. This subsection does not preclude limitation or alteration if full compensation is made by law for the full protection of the deferred fuel cost charges collected pursuant to a financing order and of the bondholders and any assignee or financing party entering into a contract with the electric utility. The Commonwealth and its agencies, including the Commission, shall not:
a. Alter the provisions of this section that authorize the Commission to create an irrevocable contract right or chose in action by the issuance of a financing order, to create deferred fuel cost property, and to make the deferred fuel cost charges imposed by a financing order irrevocable, binding, or nonbypassable charges;
b. Take or permit any action that impairs or would impair the value of deferred fuel cost property or the security for the deferred fuel cost bonds or revises the deferred fuel costs for which recovery is authorized;
c. In any way impair the rights and remedies of the bondholders, assignees, and other financing parties; or
d. Except for changes made pursuant to the formula-based adjustment mechanism authorized under this section, reduce, alter, or impair deferred fuel cost charges that are to be imposed, billed, charged, collected, and remitted for the benefit of the bondholders, any assignee, and any other financing parties until any and all principal, interest, premium, financing costs and other fees, expenses, or charges incurred, and any contracts to be performed, in connection with the related deferred fuel cost bonds have been paid and performed in full.
2. Any person that issues deferred fuel cost bonds may include the language specified in subdivision 1 in the deferred fuel cost bonds and related documentation.
K. An assignee or financing party shall not be considered an electric utility or person providing electric service by virtue of engaging in the transactions described in this section.
L. If there is a conflict between this section and any other law regarding the attachment, assignment, or perfection, or the effect of perfection, or priority of, assignment or transfer of, or security interest in deferred fuel cost property, this section shall govern.
M. In making determinations under this section, the Commission may engage an outside consultant and counsel.
N. If any provision of this section is held invalid or is invalidated, superseded, replaced, repealed, or expires for any reason, that occurrence shall not affect the validity of any action allowed under this section that is taken by an electric utility, an assignee, a financing party, a collection agent, or a party to an ancillary agreement, and any such action shall remain in full force and effect with respect to all deferred fuel cost bonds issued or authorized in a financing order issued under this section before the date that such provision is held invalid or is invalidated, superseded, replaced, or repealed, or expires for any reason.
O. As used in this section:
"Ancillary agreement" means a bond, insurance policy, letter of credit, reserve account, surety bond, interest rate lock or swap arrangement, hedging arrangement, liquidity or credit support arrangement, or other financial arrangement entered into in connection with deferred fuel cost bonds.
"Assignee" means a legally recognized entity to which an electric utility assigns, sells, or transfers, other than as a security, all or a portion of its interest in or right to deferred fuel cost property. "Assignee" includes a corporation, limited liability company, general partnership or limited partnership, public authority trust, financing entity, or other entity to which an assignee assigns, sells, or transfers, other than as a security, all or a portion of its interest in or right to deferred fuel cost property.
"Bondholder" means a person who holds a deferred fuel cost bond.
"Deferred fuel cost bonds" means bonds debentures, notes, certificates of participation, certificates of beneficial interest, certificates of ownership, or other evidences of indebtedness or ownership that are issued in one or more series or tranches by an electric utility or its assignee pursuant to a financing order, the proceeds of which are used directly or indirectly to recover, finance, or refinance Commission-approved deferred fuel costs and financing costs, and that are secured by or payable from deferred fuel cost property. If certificates of participation or ownership are issued, references in this section to principal, interest, or premium shall be construed to refer to comparable amounts under those certificates.
"Deferred fuel cost charge" means the nonbypassable charges authorized by the Commission to repay, finance, or refinance deferred fuel costs and financing costs (i) imposed on and part of all retail customer bills, except those of exempt retail access customers; (ii) collected by an electric utility or its successor or assignees, or a collection agent, in full, separate and apart from the electric utility's base rates; and (iii) paid by all retail customers of the electric utility, irrespective of the generation supplier of such customer, except for an exempt retail access customer.
"Deferred fuel cost property" includes:
1. All rights and interests of an electric utility or successor or assignee of the electric utility under a financing order, including the right to impose, bill, charge, collect, and receive deferred fuel cost charges authorized under the financing order and to obtain periodic adjustments to such charges as provided in the financing order; and
2. All revenues, collections, claims, rights to payments, payments, money, or proceeds arising from the rights and interests specified in the financing order, regardless of whether such revenues, collections, claims, rights to payment, payments, money, or proceeds are imposed, billed, received, collected, or maintained together with or commingled with other revenues, collections, rights to payment, payments, money, or proceeds.
"Deferred fuel costs" means the unrecovered amounts of previously incurred costs of fuel used to generate electricity, including the costs of purchased power, that have been deferred by an electric utility for future recovery from the utility's customers, along with financing costs on the utility's fuel deferral balance.
"Electric utility" means a Phase II Utility.
"Exempt retail access customer" means a retail customer of an electric utility that, pursuant to the provisions of § 56-577 or 56-577.1, purchased electric energy exclusively from a supplier of electric energy licensed to sell retail electric energy exclusively within the Commonwealth other than the electric utility, or that purchased electric energy from the electric utility pursuant to a Commission-approved market-based tariff, during the period when the deferred fuel costs to be financed were incurred. Such exemption shall be prorated to the extent an otherwise exempt retail customer purchased electric energy from the electric utility, in which case the retail customer shall be responsible for its pro rata share of deferred fuel cost charges authorized under a financing order.
"Financing costs" means:
1. Interest and any premium, including any acquisition, defeasance, or redemption premium, payable on deferred fuel cost bonds;
2. Any payment required under any indenture, ancillary agreement, or other financing documents pertaining to deferred fuel cost bonds and any amount required to fund or replenish a reserve account or other accounts established under the terms of any indenture, ancillary agreement, or other financing documents pertaining to deferred fuel cost bonds;
3. Any other costs related to structuring, offering, issuing, supporting, repaying, refunding, servicing, and complying with deferred fuel cost bonds, including service fees, accounting and auditing fees, trustee fees, legal fees, consulting fees, structuring adviser fees, administrative fees, placement and underwriting fees, independent director and manager fees, capitalized interest, rating agency fees, stock exchange listing and compliance fees, security registration fees, filing fees, information technology programming costs, and any other costs necessary to otherwise ensure the timely payment of deferred fuel cost bonds or other amounts or charges payable in connection with the bonds, including costs related to obtaining the financing order;
4. Any taxes and license fees or other fees imposed on the revenues generated from the collection of deferred fuel cost charges or otherwise resulting from the collection of deferred fuel cost charges, in any such case whether paid, payable, or accrued;
5. Any state and local taxes, franchise, gross receipts, and other taxes or similar charges, including regulatory assessment fees, whether paid, payable, or accrued;
6. Any costs incurred by the Commission for any outside consultants or counsel retained in connection with the securitization of deferred fuel costs; and
7. Any financing costs on the utility's fuel deferral balance prior to issuance of any fuel cost bonds, calculated at the utility's approved weighted average cost of capital.
"Financing order" means an order that authorizes the issuance of deferred fuel cost bonds; the imposition, collection, and periodic adjustments of a deferred fuel cost charge; the creation of deferred fuel cost property; the sale, assignment, or transfer of deferred fuel cost property to an assignee; and any other actions necessary or advisable to take actions described in the financing order.
"Financing party" means bondholders and trustees, collateral agents, any party under an ancillary agreement, or any other person acting for the benefit of bondholders.
"Financing statement" has the same meaning as provided in § 8.9A-102 of the Uniform Commercial Code.
"Phase II Utility" has the same meaning as provided in subdivision A 1 of § 56-585.1.
"Pledgee" means a financing party to which an electric utility or its successors or assignees mortgages, negotiates, pledges, or creates a security interest or lien on all or any portion of its interest in or right to deferred fuel cost property.
§ 56-249.7. Certain directors and officers of utility to file shareholder information.The directors and officers of any public utility as defined in § 56-232 shall file with the Commission a record of all officers and directorships and all sources of income in excess of $25,000 per year arising from voting securities in all other corporations which to the knowledge of the director or officer furnishes fuel with a value in excess of $50,000 per year to the public utility. Such records for the past year shall be filed or made current on or before September 1 of each year.
1985, c. 522.
§ 56-250. Commission may authorize action by public utility in time of emergency or shortage; plans.(1) Whenever it shall appear by satisfactory evidence that any public utility furnishing in this State power, heat, light or water cannot supply all of its customers the usual requirements of each by reason of strikes, accidents, want of fuel, or for any other reason, the Commission may authorize such public utility to take such action as, in the opinion of the Commission, will minimize adverse impact on the public health and safety and facilitate restoration of normal service to all customers at the earliest time practicable.
(2) To facilitate implementation of this section, the Commission may require any such public utility to file, as a part of the rules and regulations referred to in § 56-236, its plan for curtailment of service in such a condition of emergency or shortage. Such plans shall be considered and shall take effect in the manner provided in this chapter for the schedules of rates and charges and rules and regulations of public utilities.
1920, p. 232; Michie Code 1942, § 4072a; 1974, c. 478; 1975, c. 358.
§ 56-251. Repealed.Repealed by Acts 1974, c. 478.
§ 56-253. Existing remedies retained.Nothing contained in this chapter shall in any way abridge or alter the remedies at common law, in equity, or by statute, but the provisions hereof shall be deemed to be in addition to such remedies.
Code 1919, § 4073.